Plan Number: T20PRE0122
Parcel: Unknown

Address:
1121 S 11TH AV

Review Status: Completed

Review Details: PREAPPLICATION LABELS

Plan Number - T20PRE0122
Review Name: PREAPPLICATION LABELS
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/16/2020 ANDREW CONNOR LANDSCAPE REVIEW Completed Show compliance with landscaping and screening requirements by locations, material descriptions, and dimensions. Specific plant or hardscape material shall be detailed on a landscape plan. A detailed landscape plan is required. In accordance with Section 2-10.0.0, Landscape Plan Requirements.
09/21/2020 ZELIN CANCHOLA COT NON-DSD TRAFFIC Reqs Change No adverse comments. Standard requirements will apply.
09/24/2020 ELISA HAMBLIN ZONING REVIEW Completed CDRC Thursday Pre-Submittal Transmittal
PDSD Zoning Review

FROM: Nicholas Martell; Planner
PROJECT: Thursday Pre-submittal meeting – T20PRE0122
Address: 1121 S 11th Av
Parcel(s): 117091080
Zoning: C-3
Existing Use: Vacant
Proposed Use: Multifamily Development

TRANSMITTAL DATE: September 24, 2020

COMMENTS:
1. Development must comply with the Administrative Manual Section 2-06 - Development Package.
2. The proposed use is Multifamily Development, which is permitted in the C-3 zone.
3. Development standards such as setbacks and height appear to be met.
4. Provide square footage of all units in order to determine parking requirements. Provided parking appears adequate if the proposed units are less than 400 square feet.
5. Provide required bike parking on site. With 20 units, a total of 2 short-term and 10 long-term spaces are required.
6. Provide accessible parking on site.
7. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards.

If you have any questions please contact me at nicholas.martell@tucsonaz.gov or (520) 837-4966.
09/24/2020 SBEASLE1 TUCSON WATER NEW AREA DEVELOPMENT REVIEW Reqs Change 300 - 330 pm - T20PRE0122 - 1121 S 11TH AV - SiteGradingDDOPDMR 11th Ave. Development

- There is an 12" Ci water line (PN 165-1997) is in 11th Av. There is a 6" Fire Hydrant near the Northwest corner of the property. 3/4" meter on a 1" service line serving the property currently.

- To further discuss options for obtaining water service further, please contact Mr. Ray Munoz or Mr. Jeremiah Jenkins at 837-2207 in the Tucson Water New Services Section to discuss:
o Potential points of connection for the waterline extension to Tucson Water's existing water distribution system.
o The number of water service lines, water meters, and meter sizes, necessary to serve this development.
o The advantages and disadvantages of installing the necessary water meters via Tucson Water's Job Order Contract (JOC) process.
o Please note that if hydraulic modeling is necessary to verify which potential points of connection have the capacity necessary to serve the proposed development, it can be done as part of Tucson Water's Job Order Contract (JOC) process.

All questions, comments or concerns about these comments may be addressed to:
Fabien Elenes, Engineering Associate
Tucson Water, New Development Section
310 W. Alameda St.
P.O. Box 27210, Tucson, AZ 85726-7210
(520) 837-2202, Fabien.Elenes@tucsonaz.gov
09/24/2020 LOREN MAKUS ENGINEERING REVIEW Completed 1. This is not in a balanced or critical basin. Retention and detention are not required.
2. Show access to the solid waste enclosures.
3. Maximize water harvesting.
4. Back-up spur required.
09/29/2020 SBEASLE1 COT NON-DSD FIRE Needs Review * Aerial access required. Not feasable with current layout.