Plan Number: T20PRE0114
Parcel: Unknown

Review Status: Completed

Review Details: PREAPPLICATION

Plan Number - T20PRE0114
Review Name: PREAPPLICATION
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/08/2020 ANDREW CONNOR LANDSCAPE REVIEW Completed Show compliance with landscaping and screening requirements by locations, material descriptions, and dimensions. Specific plant or hardscape material shall be detailed on a landscape plan. A detailed landscape plan is required. In accordance with Section 2-10.0.0, Landscape Plan Requirements.
09/08/2020 GDAURIA1 COT NON-DSD FIRE Completed * Hydarants must be located within 400' of any exterior portion of any building.
09/14/2020 ZELIN CANCHOLA COT NON-DSD TRAFFIC Completed No adverse comments. Standard requirments will apply.
09/16/2020 LOREN MAKUS ENGINEERING REVIEW Completed 1. Site is in neither balanced nor critical basin.
2. Alternate sidewalk location requires TSMR.
3. Five-year threshold retention required.
4. Show driveway/garage locations to demonstrate space remains on street for parking spaces.
09/16/2020 SBEASLE1 TUCSON WATER NEW AREA DEVELOPMENT REVIEW Completed 200 - 230 pm - T20PRE0114 - 2451 S CAMPBELL AV - SiteGrading FLD Campbell Ave & 36th St

1. TucsonWater has an existing 6" cement asbestos water main (PN FN271A) in Campbell Avenue, an existing 6" cement asbestos water main (PN FN271A) in34th St., and an existing 4" cement asbestos water main (PN FN271A) in Kramer Avenue that can serve this project.
2. The design of the on-site water mains will need to go through Tucson Water's Master Water Plan process, and Design Plan process.
3. During the design of the on-site water mains, please plan on all of the following:
a. Locating the on-site water mains in the private streets, which will need to be dedicated as public utility easements by the final plat.
b. Looping the on-site water mains to the maximum extent practicable, and
c. Connecting on-site water mains to multiple points in Tucson Water's existing water distribution system.
4. Any questions, comments or concerns about these comments may be addressed to:

Tim Rowe, Sr. Engineering Associate
Tucson Water, New Development Section
310 W. Alameda St.
P.O. Box 27210
Tucson, AZ 85726-7210
(520) 837-2106
tim.rowe@tucsonaz.gov
09/17/2020 ELISA HAMBLIN ZONING REVIEW Completed CDRC Thursday Pre-Submittal Transmittal
PDSD Zoning Review

FROM: Elisa Hamblin, AICP; Principal Planner

PROJECT: Thursday Pre-submittal meeting – T20PRE0114
Address: 2451 S Campbell Av
Parcel(s): 13005303H
Zoning: C-1; R-2
Existing Use: Residential
Proposed Use: Residential; FLD

TRANSMITTAL DATE: 9/17/2020

COMMENTS:
1. Development must comply with the Administrative Manual Section 2-06 - Development Package.
2. The proposal is for development of a Flexible Lot Development (FLD), which is a permitted use subject to use-specific standards 8.7.3.
3. Development standards such as density, functional open space and setbacks appear to be met.
4. Visitor Parking is calculated correctly, but it is unclear how the on-street parking will function with the garages. Please clarify the size of all parking spaces and that sufficient access and maneuverability is provided.
5. Ensure that there is continuous pedestrian circulation throughout the site (7-01.3.0 Technical Standards). The southwest units appear to have sidewalk access, but said access needs to continue to Campbell Ave.
6. Please note, per UDC Article 8.7.3.M.1.B.1, submittal of an Architectural Variation Plan (AVP) will be required. The AVP is triggered due to the proposal exceeding 20 single-family residences.
7. Please note, per UDC Article 8.7.3.M.2.A, a Privacy Mitigation Plan (PMP) will be required. The PMP is triggered due to the adjacency to existing residential development.
8. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards.

If you have any questions please contact me at elisa.hamblin@tucsonaz.gov or (520) 837-4966.