| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/04/2020 | ANDREW CONNOR | LANDSCAPE | REVIEW | Completed | Show compliance with landscaping and screening requirements by locations, material descriptions, and dimensions. Specific plant or hardscape material shall be detailed on a landscape plan. A detailed landscape plan is required. In accordance with Section 2-10.0.0, Landscape Plan Requirements. |
| 08/07/2020 | GDAURIA1 | COT NON-DSD | FIRE | Completed | * Fire sprinklers required. * If high piled storage, building must have emergency access doors not to exceed 125' to the next. * Fire Aerial Access required on east-side of building complying with IFC D105. |
| 08/17/2020 | ZELIN CANCHOLA | COT NON-DSD | TRAFFIC | Completed | No adverse comments, standard requirements will apply. Weiding/Genter St - New crb and sidewalk Tucson Blvd - Rebuild Driveways to meet current standard. A traffic statement required to include if decel lane is warranted for driveays. |
| 08/19/2020 | ELISA HAMBLIN | ZONING | REVIEW | Completed | CDRC Thursday Pre-Submittal Transmittal PDSD Zoning Review FROM: Elisa Hamblin, AICP; Principal Planner PROJECT: Thursday Pre-submittal meeting – T20PRE0104 Address: 6360 S Tucson Bl Parcel(s): 14028022F Zoning: P-I and I-1 Existing Use: Vacant Proposed Use: General Manufacturing TRANSMITTAL DATE: August 19, 2020 COMMENTS: 1. Development must comply with the Administrative Manual Section 2-06 - Development Package. 2. The proposed General Manufacturing use is permitted in the P-I and I-1 zone, subject to use specific standards 4.9.5.C.2, .4, .5, .6, 7, & .8 and 4.9.13.Q 3. Development standards such as parking, setbacks and building height appear to be met. 4. Pedestrian access (sidewalk/crosswalk) is required from each street. 5. Ensure compliance with use-specific standards 4.9.5.C.5 “Loading and unloading areas, docks, and platforms, shall be located entirely within a building or an area on the lot that shall be enclosed on all sides by a solid wall or fence six feet in height.” 6. Ensure compliance with use-specific standards 4.9.5.C.8 “Outdoor storage, when permitted, shall not be located in a street perimeter yard. Outdoor storage areas shall be screened in accordance with Section 7.6, Landscaping and Screening. No materials or products shall be stacked or stored to exceed the height of the screen within 50 feet of an adjoining residential zone or street . Outdoor display of finished products is permitted within a street perimeter yard in an area limited to 10% of the site area or 10,000 square feet, whichever is less. Such display area shall not encroach into required landscape buffer areas. Outdoor storage in the P-I zone is limited to 25% of the site area. “ 7. The site is located within the Airport Environs Zone for TIA. Ensure standards of Compatible Use Zone 2 and the height overlay are met. 8. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards. If you have any questions please contact me at elisa.hamblin@tucsonaz.gov or (520) 837-4966. |
| 08/19/2020 | LOREN MAKUS | ENGINEERING | REVIEW | Completed | 1. Critical basin retention and detention is required. 2. Maximize water harvesting. 3. Check turning radius for tractor-trailer combinations. |
| 08/20/2020 | SBEASLE1 | TUCSON WATER NEW AREA DEVELOPMENT | REVIEW | Completed | 300 - 330 pm - T20PRE0104 - 6360 S TUCSON BL - SiteGradingSWPPP - Daybreak Industrial 1. There are existing 8" water mains in Ginter Rd., Tucson Blvd., and Wieding Rd. adjacent to the north, east and south sides of this property, and there is an existing fire hydrants on the northeast corner of the property. 2. After the water demands for this project have been determined (typically, via a water fixture unit count has been conducted for the project using the 2018 International Plumbing Code) and the fire flow requirements have been established by the local fire authority, please contact Mr. Ray Munoz or Mr. Jeremiah Jenkins at 837-2207 in the Tucson Water New Services Section to discuss: a. Potential points of connection to Tucson Water's existing water distribution system. b. The number of water service lines, water meters, and meter sizes, necessary to serve this development. c. The advantages and disadvantages of installing the necessary water meters via Tucson Water's Job Order Contract (JOC) process. 3. If hydraulic modeling is necessary to verify Tucson Water's existing water distribution system can supply the required fire flow, it can be done as part of the JOC process. 4. Any questions or concerns about these comments should be addressed to: Tim Rowe, Sr. Engineering Associate Tucson Water, New Development Section 310 W. Alameda St. P.O. Box 27210 Tucson, AZ 85726-7210 (520) 837-2106 tim.rowe@tucsonaz.gov |