Plan Review Detail
Review Status: Completed
Review Details: PIA - SUBMITTAL
Plan Number - T20PI00015
Review Name: PIA - SUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/24/2020 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Completed | |
09/24/2020 | RLEIGH1 | UTILITY CLEARANCES | COT STREETS DIVISION | Needs Review | |
09/24/2020 | ZELIN CANCHOLA | DOT TRAFFIC | REVIEW | Completed | |
09/24/2020 | ERNIE ENCINAS | DOT_ELEC | REVIEW | Approved | |
09/24/2020 | JIM FEMLING | DOT STREET MAINTENANCE | REVIEW | Completed | |
09/24/2020 | RLEIGH1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Needs Review | |
09/24/2020 | RLEIGH1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Needs Review | |
09/24/2020 | RLEIGH1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Needs Review | |
09/24/2020 | RLEIGH1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Needs Review | |
09/24/2020 | RLEIGH1 | UTILITY CLEARANCES | COX COMMUNICATION | Needs Review | |
09/24/2020 | RLEIGH1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Needs Review | |
09/24/2020 | RLEIGH1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Needs Review | |
09/24/2020 | RLEIGH1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Needs Review | |
09/28/2020 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Reqs Change | September 24, 2020 SUBJECT: Paving Plans for Saguaro Trails Block 6, Phase II PROJECT REVIEWER: Richard Leigh, TDOT, TDOT Eng. Review RESUBMITTAL REQUIRED: TDOT Permit Review Section has reviewed the subject PIA paving plan and does not recommend approval at this time. The following comments need to be addressed and plans revised prior to resubmittal. Please include a response letter addressing the following comments and return redlined drawings with subsequent submittal. 1. Add the plan number “I-2020-015” in the title block of each sheet. 2. Add PIA activity number “T20PI00015” on coversheet. 3. Add Development Plan number on coversheet. 4. Add subdivision plat number on cover sheet. 5. Label and provide details for proposed curb transitions. 6. Label all curb BC’s and EC's with stationing, offsets and elevations. 7. Sheet 2: Revise note 3 to indicate that AC will conform to PAG's Replacement Specification for Section 406 Asphaltic Concrete, dated December 12, 2019. The surface layer shall be a PG 76-22TR+. 8. Sheet 9: “Alternate Sidewalk Location” detail This detail should be revised to provide a 2' buffer between the curb and sidewalk. TSM requires a 2’ buffer and this configuration will not work in areas where parking is permitted If you have any questions, I can be reached at 520-237-8692 or emailed at Richard.Leigh@tucsonaz.gov. |
10/26/2020 | RICHARD LEIGH | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSSADOR | Completed | |
10/26/2020 | RICHARD LEIGH | PIA COORDINATOR | OUT TO CUSTOMER | Completed |