| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/04/2021 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Needs Review | |
| 01/04/2021 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. Provide a complete electrical line diagram, include: (a) Voltage, phase, amp, AIC, ratings of the electrical service equipment. (b) Location of the main electrical service equipment on the property. (c) 2 ground rods required per NEC 250. (d) If the electrical service is to be installed under a separate permit, please indicate this on the plan. Ref; 2018 IBC sec, 107.2.1, 2017 NEC, 2018 IECC, City of Tucson Commercial Plan Submittal Requirements. |
| 01/04/2021 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet G-1; Notes: Note 1 references the 2015 IBC for fire separation distances. Please revise the reference and distances as required. Please verify the IBC Section 705.3 (Exception1) distance requirements are met for buildings on the same lot. 2. Sheet G-1; Design Criteria: Please indicate the 2010 ADAAG accessibility code in this list. 3. Sheet S-1; Foundation Plan Boxed Note: This note indicates "Foundation to be designed and installed by others. Current design is for illustration purposes only and is not for construction". In order to approve these drawings for construction, final structural calculations and drawings must be provided for review. 4. General: Please provide written responses to all review comments. |
| 01/06/2021 | JPEELDA1 | FIRE | REVIEW | Approved | |
| 01/07/2021 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Provide a site plan showing the installation of the water service to the building and the installation of the building sewer. Specify the materials of construction. Reference: Sections 104.2 and 107.2.1, IBC 2018. |
| 01/07/2021 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Passed | |
| 01/07/2021 | ROBERT SHERRY | WATER | REVIEW | Reqs Change | Show the location of the proposed water meter, backflow preventer, and the water service pipe on a site plan. Reference: Section 107.2.1 and 107.2.6, IBC 2018. |
| 01/14/2021 | NICHOLAS ROSS | ZONING | REVIEW | Reqs Change | DP20-0241must be approved first. |
| 02/02/2021 | LOREN MAKUS | ENGINEERING | REVIEW | Reqs Change | Development package must be approved first. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 02/03/2021 | IMONSHI1 | OUT TO CUSTOMER | Completed |