Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO
Permit Number - T20CM08681
Review Name: RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/13/2021 | NICHOLAS ROSS | ZONING | REVIEW | Approved | |
01/13/2021 | DTRAMME1 | ENGINEERING | REVIEW | Passed | |
01/13/2021 | ANDREW CONNOR | NPPO | REVIEW | Passed | |
01/13/2021 | KEN VAN KARSEN | BUILDING-RESIDENTIAL | REVIEW | Reqs Change | T20CM08681 PLAN REVIEW COMMENTS Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. In order to facilitate a shorter back check time, please provide updated plans and calculations with a written response to each of the notated items indicating action taken. Do not cloud the changes made for comment revisions. SCOPE OF REVIEW: The scope of this plan review covers architectural, plumbing, mechanical, energy conservation and electrical. All code references are to the 2018 International Residential Code and 2018 International Energy Conservation Code. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions and concerns before permit approval. GENERAL COMMENTS: 1. Show compliance with the Inclusive Home Design Ordinance adopted by the City of Tucson Ordinance #10463 on 10/16/2007. Notate accessible route, minimum door width, changes in floor elevation, door hardware, electrical outlet reach range, grab bar reinforcement, etc. 2. All SFR and Duplex plans submitted after July 1, 2009 require a solar photo-voltaic system, or future installation preparation City of Tucson Ordinance #10549 . a. Show a minimum 300 SF clear solar-ready zone on a roof or framing plan, T103.3. Model plans should show four typical south facing roof surfaces. b. Label a double breaker space for future Photo Voltaic on the panel schedule opposite end from the main/supply side, T103.9. 3. When the clothes washer is not near an exterior wall show a gray water bathing fixture drain looped 3’ beyond an exterior wall below grade before connection to the building drain. See details at https://www.tucsonaz.gov/files/pdsd/codes-ordinances/Grey_Water_Options_FINAL_.pdf Update the gray water pipe shown without connection to the HCS. FLOOR PLANS: 1. Show a maximum ½” floor elevation changes at a notated accessible route entrance on the floor plan, R106.1.1. Include all threshold conditions for a route from the exterior into the living space. SECTIONS - DETAILS: 1. Clarify the placement of ceiling/roof insulation for determining the need for attic ventilation, R806. 2. An unvented roof assembly requires an air-impermeable rigid insulation material with a minimum R-5 value applied correctly to either side of the roof sheathing, R806.5. Show a roof design with insulation types and minimum thickness for meeting the condensation control requirement and the minimum total insulation value of R-38. PLUMBING PLANS: 1. Show hot water pipe with minimum R-3 insulation, N1103.4.2. Show compliance with the maximum length of hot water piping shall not exceed 50’, IPC607.2. MECHANICAL PLANS: 1. Provide (an HVAC system with fresh air intake) whole-house mechanical ventilation, or controlled exhaust with a calculated airflow rate, R303.4; N1103.6 & M1505.4. Show the system and appropriate flow rate setting on the plans. A four bedroom dwelling of 1501 – 3000 SF requires a 75 CFM continuous setting. Update the plan notation. OUTDOOR LIGHTING CODE 1. Show the proposed fixture as full cut-off FCO style or provide an Outdoor Lighting Calculation including all exterior fixtures on the property for determining exterior lighting limits. Adjustable security light fixtures are unshielded, not FCO. INTERNATIONAL ENERGY CONSERVATION CODE: 1. Energy Certificate: (Mandatory) place near the indoor furnace or in utility room, N1101.14. Add notation to plans. If you have any questions, please contact: Ken Van Karsen (520) 837-4912 City of Tucson Residential Plan Review |
01/21/2021 | JPEELDA1 | FIRE | REVIEW | Denied | Your house is over 3,600 sq feet so you will need to have Tucson water perform a model for your house. We need two items met: 1) 1,750 gpm for 2 hours 2) a hydrant located within 400' of your house. I have copied Walid with Tucson Water. He can perform the model and send the letter. If the two conditions are met, you will be good to go and I can approve your plans. If they are not met, then you will need to add fire sprinklers to your house. Please contact me if you have any questions. |