Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: REVISION - - 1ST
Permit Number - T20CM08394
Review Name: REVISION - - 1ST
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
10/28/2021 | STANTEC | 2ND PARTY REVIEW | REVIEW | Reqs Change | Activity Number: T20CM08394 REV1 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. ARCHITECTURAL COMMENTS Sheet 0x1.3 1. This sheet has been modified to show new locations for 4 charging stations placed to one side of each of 4 light pole locations, believed to be serving back-to-back charging stations; however, Sheet 5e0.3 shows 12 new charging station locations, believed to be serving parking spaces back-to-back, and placed on both sides of each of the parking lot poles. Please coordinate. Also, it looks as if these charging stations are currently not entirely developed; there are empty conduits and pedestals only. Please clarify on the plans. Sheets 0x1.8, 0x1.9, 0x1.10 1. The gates have had added notes indicating “power conduit to office building, see electrical site plan; however, there is no electrical information in the revised drawings or the approved building set regarding electrical for these gates. Please coordinate. Sheet 5a8.0 1. Several of the doors have had their hardware numbers changed; please provide a door hardware schedule so that the changes can be evaluated. STRUCTURAL COMMENTS There are no comments. MECHANICAL COMMENTS There are no comments. PLUMBING COMMENTS There are no comments. ELECTRICAL COMMENTS Sheets 0x1.8, 0x1.9, 0x1.10 1. The gates have had added notes indicating “power conduit to office building, see electrical site plan; however, there is no electrical information in the revised drawings or the approved building set regarding electrical for these gates. Please coordinate. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
10/28/2021 | NGARCIA3 | OUT TO CUSTOMER | Completed |