Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: REVISION - - 1ST
Permit Number - T20CM07995
Review Name: REVISION - - 1ST
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/20/2021 | STANTEC | 2ND PARTY REVIEW | REVIEW | Reqs Change | ARCHITECTURAL COMMENTS Sheet A-000.1 1. Some new sheets have been added to the revised set of drawings. Some of these sheets are missing from the List of Drawings; specifically, Sheets S5.7, P-006, and E-107; please update. {E-106 is also missing from the List of Drawings.} Sheet A-307 1. The currently approved permitted sheet has a Delta 2 dated 3/11/21, whereas the “revised” sheet has a Delta 1B dated 2/19/21. When comparing these sheets further, there is no discernable difference in the information contained. Please clarify. Sheet A-400 1. Sheets A-405 thru A-409 have been removed and replaced by Sheets A-405A thru A- 405C and A-406A thru A-406C. While reviewing the new hardware schedules on Sheets A-406A thru A-406C, they appear to align with the hardware within the Interior Door and Frame Schedule. For example, Hardware Set TI-9A within the Interior Door and Frame Schedule exists in the hardware schedules on Sheets A-406A thru A-406C. However, none of the nomenclature in the hardware sets on Sheets A-405A thru A-405C align with any of the door schedules. For example, where does Hardware Set S-02D occur in the door schedules? Please coordinate. STRUCTURAL COMMENTS Sheets S2.1 and S2.2 1. There are new foundation elements indicated on the foundation plans (i.e., what appears to be steel posts bearing on the slab and MHE column footings identified by Detail 20 on Sheet SD2), where are the calculations for these foundations? Do these foundations support raised equipment platforms? If so, where is the design for these raised equipment platforms? Are these raised equipment platforms to be added to this permit’s list of deferred submittals, or will they be part of some future tenant improvement? Please clarify. MECHANICAL COMMENTS There are no comments. PLUMBING COMMENTS There are no comments. ELECTRICAL COMMENTS Sheets E-100 and E-106 1. The enlarged plans on Sheet E-106 do not match the site plan on Sheet E-100; please coordinate. {Is the proposed Truck EV distribution equipment and utility company transformer within the yard fence or is it not?} |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
04/20/2021 | ARUIZ1 | OUT TO CUSTOMER | Completed |