Permit Review Detail
Review Status: Completed
Review Details: RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO
Permit Number - T20CM07903
Review Name: RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 11/25/2020 | ANDREW CONNOR | NPPO | REVIEW | Passed | |
| 12/10/2020 | KEN VAN KARSEN | BUILDING-RESIDENTIAL | REVIEW | Completed | |
| 12/18/2020 | SBLOOD1 | ENGINEERING | REVIEW | Passed | |
| 12/31/2020 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | ZONING REVIEW TRANSMITTAL FROM: Steve Shields Site Section Manager PROJECT: T20CM07903 4137 E Paseo Dorado Master Bedroom & Garage Addition TRANSMITTAL: Date COMMENTS: the following comments are relative to an application for a Design Development Option (DDO) (UDC 3.11.1). This site is located in the R-1 zone (UDC 4.7.1). A single-family residence (SFR) is a permitted use in this zone (Table 4.8-2). See Use-Specific Standards 4.9.7.B.5 - 9. 10. The minimum setback is the greater of six (6) feet, or two-thirds (2/3) the height of the structure’s wall facing each interior property line greater of the two. (Table 6.3-2.A). The wall height measurement is based on a dimension from design grade to the highest point of the wall. As a dimension was not provide from design grade 6” is added to height provided from finished floor. 1. Based on a wall height of 12’-6” for the proposed garage addition the required perimeter yard setback is 8’-4”, proposed is 6’-6”. 2. Based on a wall height of 14’-6” for the new parapet wall along the east property line the required perimeter yard setback is 8’-4”, proposed is 9’-8”. 3. Based on a wall height of 13’-6” for the proposed bedroom addition the required perimeter yard setback is 8’-4”, proposed is 9’-0”. The height measurement was based on a measurement taken in Bluebeam as no height dimension was provided on the plans. A Design Development Option (DDO) application must be submitted and approved priot to approval of these plans. DDO application and submittal requirements can be found at: https://www.tucsonaz.gov/files/pdsd/forms/DDO_for_Setback_and_Height_UDC_8.11.20.pdf |