Permit Number: T20CM06862
Parcel: 10408078C

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T20CM06862
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/20/2020 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Passed
10/20/2020 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Passed
10/20/2020 ROBERT SHERRY WATER REVIEW Passed
10/21/2020 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Passed
10/21/2020 JPEELDA1 FIRE REVIEW Approved
10/26/2020 STEVE SHIELDS ZONING REVIEW Reqs Change CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: Steve Shields
Section Manager

PROJECT: T20CM06862
Holmes Tuttle - Metal Shade Structure
660 W Auto Mall Dr

TRANSMITTAL DATE: October 26, 2020

DUE DATE: October 26, 2020

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

1. A development package is required to be submitted and approved prior to approval of this building plan. Provide a copy of the last approved Development Package DP18-0006 with the area of work clouded and a detail demonstrating the perimeter yard setbacks are met. Submit this under the Development Package and Land Division/Subdivision Application found at: https://www.tucsonaz.gov/files/pdsd/forms/Development_Package_and_Land_Division-Subdivision_Application.pdf

If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
11/09/2020 SBLOOD1 ENGINEERING REVIEW Reqs Change A development package is required to be submitted and approved before this building plan can be approved.

Stephen Blood
stephen.blood@tucsonaz.gov
11/10/2020 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Approved
11/10/2020 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed