Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T20CM06675
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
10/07/2020 | ROBERT SHERRY | WATER | REVIEW | Reqs Change | 1. Provide plans sealed by an Arizona Registrant. Reference: Arizona Revised Statutes 32-125, Board of Technical Registration Rules R4-30-304 2. Reduced pressure backflow prevention assemblies are required to be installed in locations accessible to Tucson Water. Reference: Chapter XXVII, Article V, Section 27-72, the Tucson Code, http://www.tucsonaz.gov/files/water/docs/backflow-ordinance.pdf 3. Show the location of the proposed water meter, backflow preventer, and the water service pipe on a site plan. The development package is not a substitute for a complete site plan. Reference: Section 107.2.1 and 107.2.6, IBC 2018. 4. Provide the size of the water meter serving this building, the size of the backflow preventer associated with the water meter, and the total water demand served by the water meter. Reference: Section 107.2.1, IBC 2018. |
10/08/2020 | JPEELDA1 | FIRE | REVIEW | Approved | |
10/14/2020 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | PDSD TRANSMITTAL FROM: Steve Shields Section Manager PROJECT: Door Church Sanctuary 2950 E Irvington Rd T20CM06675 (1st Review) TRANSMITTAL DATE: October 14, 2020 1. Zoning has reviewed the building plans for compliance with the submitted development package, DP20-0093, but until the DP is approved Zoning cannot approved the building plan. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 |
10/29/2020 | SBLOOD1 | ENGINEERING | REVIEW | Reqs Change | 1. Roof Plan A1.4 is missing from plan set 2. DP needs to be approved before building plans can be approved Stephen Blood stephen.blood@tucsonaz.gov |
11/10/2020 | STANTEC | ELECTRICAL-COMMERCIAL | REVIEW | Completed | |
11/10/2020 | STANTEC | PLUMBING-COMMERCIAL | REVIEW | Completed | |
11/10/2020 | STANTEC | BUILDING-COMMERCIAL | REVIEW | Completed | |
11/10/2020 | STANTEC | MECHANICAL-COMMERCIAL | REVIEW | Completed | |
11/10/2020 | ARUIZ1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Needs Review |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
11/10/2020 | ARUIZ1 | OUT TO CUSTOMER | Completed |