Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T20CM06322
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/16/2020 | JPEELDA1 | FIRE | REVIEW | Approved | |
09/16/2020 | ROBERT SHERRY | WATER | REVIEW | Completed | |
09/16/2020 | LOREN MAKUS | ENGINEERING | REVIEW | Reqs Change | 1. Development package must be approved first. 2. Ensure sidewalks are maintained flood-free for up to a 10-year event. |
09/18/2020 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. Revise the 2012 IECC lighting Comcheck using the current 2018 IECC. 2. Ref; Plan Sheet E1.2, Outdoor Lighting Code Compliance. Concerning the lighting note, The Outdoor Lighting Code calculations and compliance requires some process of Engineering Design and falls under the responsibility of the Registrant of Record not the contractor. Provide plans and evidence on the plans that the proposed exterior lighting fully complies with the Outdoor Lighting Code. See section 104 for plan submittal requirements. Provide lighting plans with the following information on the plans; (a) Provide a complete luminaire schedule. (b) Size of the parcel in acres. (c) See table 401.1, lighting area and option and indicate this information in the lighting site plan, also showing the locations and types of all exterior luminaires including existing. (d) 402.1 (light source color temperature requirements), shielding requirements, etc . (e) Provide calcs for total lumens allowed and total lumens proposed per acre including existing, for Full Cut Off and Unshielded per table 401.1. (f) Indicate whether or not a special inspection is required per sec. 104.2.2, and 106.2. (g) Specify any exceptions used. (h) Curfew lighting controls If applicable. Do not confuse the Outdoor Lighting Code with the IECC. Ref; 2017 NEC, 2012 Tucson/Pima County Outdoor Lighting Code (OLC), 2018 IBC sec 107.2.1. 2018 IECC. |
09/21/2020 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Provide the civil utility drawing referenced on sheet P1.0 showing the location of the water meter, backflow preventer, the route of the water service pipe, the size, route, and slope of the building sewer, the location of all cleanouts in the building sewer, and the location of the connection of the building sewer to the public sewer. Reference: Section 107.2.1, IBC 2018. 2. Complete detail 2/P3.1 (Plumbing Drain, Waste, and Vent Riser) i.e. connect the grease interceptor to the building drain. Reference: Section 107.2.1, IBC 2018. 3. The design of the water heater piping, with shutoff valves located between the water heater and the expansion tank, makes it impossible for the expansion tank to accommodate the thermal expansion of the water in the water heater, as intended by Section 607.3, IPC 2018. Reference: Section 303.2, IPC 2018. 4. Hand sinks in the kitchen are allowed to connect to the sanitary waste system instead of the grease waste system only if each sink has a sign posted above it that states, "HANDWASH SINK ONLY! NO FOOD PREPARATION OR DISHWASHING ALLOWED." Reference: Section 1003.3, IPC 2018, as amended by the City of Tucson. 5. Provide the opening dimensions for the primary and overflow scuppers for the roofs over the drive-thru areas. Reference: Section 1106.5, IPC 2018. |
09/22/2020 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet G1.0; Code Analysis (Applicable Codes): Please remove the 2010 ADA Code reference and add the 2009 ICC/ANSI A117.1 Accessibility Code. 2. Sheet G1.0; Code Analysis (Plumbing Fixture Count): This Table indicates 100 total occupants. Please revise. 3. Sheet S1.1; Keynotes (06a): Keynote 06a was not located on the plan. Please verify. 4. Sheets S1.1, S1.2, S1.3, and S5.9; Plans: Please add north arrows to all plans. 5. Sheet S1.1; Plan Notes (2): In Note 2, please complete the civil elevation. 6. Sheet S1.0; Foundation Plan: Please add a column footing schedule and a wall footing schedule to this sheet. There are footings on the plan that do not define the footing size or extent. 7. Sheet S1.1; Foundation Plan: At Shear Wall 2 on Grid 3.1, Section C1/S5.3 is cut and indicates a 1'-0" foundation. The Foundation Plan indicates the footing is 1'-6" wide (9" + 9"). Please coordinate. 8. Sheet S1.1; Foundation Plan: All interior shear walls indicate Section C1/S5.3, which is a 1'-0" foundation. However, the plan indicates a 1'-6" foundation width at these partitions. Please coordinate. 9. Sheet S1.2; Plan Notes (3): Please complete the mechanical unit weight limits in this note. 10. Sheet S1.2; Keynotes (12): Note 12 references Sheet S5.10 for an enlarged framing plan. Please revise that reference. 11. Sheet S1.2; Roof Framing Plan: At interior shear wall 5, a Section C5/S5.4 is cut. Please revise that section cut reference. 12. Sheet S5.1; Detail D4: Please provide structural calculations for the light pole foundation. 13. Sheet S5.1; Detail D5: Please provide structural calculations for the flag pole foundation. 14. Sheet S5.8; Detail A4: Please provide structural calculations for the menu board foundation. 15. Sheet S5.8; Detail C5: Please provide structural calculations for the headache bar foundation. 16. Sheet A0.1; Keynotes (163): Please indicate in this note the sign permit will be separate from this building permit. 17. Sheet A1.3; Reflected Ceiling Plan: Please indicate all exit lighting on this sheet, or reference a sheet that includes that information. 18. Sheet A1.3; Keynote Legend (137): Please complete that note. 19. Sheet A1.4; Keynote Legend (162): Note 162 references Detail A1/A5.3. Please revise that reference. 20. Sheet A5.4; Partition A: At the top of the partition, please indicate the lateral bracing size, and how it is connected to the roof and to the top of the partition. 21. General: Please provide a Special Inspection Certificate with Parts A and B completed. This certificate may be found at www.tucsonaz.gov/PDSD. 22. General: Please provide written responses to all review comments. |
09/22/2020 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. The COMcheck envelope assembly description for the building roof calls for R-25 cavity insulation and R-13 continuous insulation but the building and roof sections show R-25 continuous insulation and no cavity insulation. Revise the energy code analysis for the building envelope, coordinating the building components used in the analysis with those shown on the drawing. Reference: Section C303.1, IECC 2018, as amended by the City of Tucson. 2. Provide heating and cooling load calculations to justify the heating/cooling capacities of the specified HVAC units. Reference: Section C403.1.1 and C403.3.1, IECC 2018. 3. Show that the walk-in cooler/freezer meets the construction requirements of Section C403.10.2, IECC 2018. 4. Show that the walk-in cooler/freezer meets the efficiency requirements of Section C403.10.2.1, IECC 2018. 5. Provide a design for the proposed kitchen exhaust system that clearly shows that the installation will comply with the requirements of Sections 302, 304, 506, 507, and 508, IMC 2018. Reference: Section 107.2.1, IBC 2018 6. Provide structural calculations and details to show that the two Type I grill hoods are supported from the building structure in accordance with Section 507.2.4, IMC 2018 (the hood hanging weight plus the weight of personnel working in or on the hood). Reference: Section 302.1, IMC 2018. 7. Show that the hood installations comply with Section 507.2.6, IMC 2018 for clearances (i.e. 18" clearance from combustible materials or a non-combustible structure, a layer of gypsum wallboard and a smooth, cleanable, non-absorbent, and non-combustible material installed between the hood and the wall, and extending 18" beyond the hood). A wood stud structure within 18" of a Type I hood is not acceptable. 8. The kitchen floor plan (K1.1) shows two 6-foot grills, one "6 foot grill hood" and one exhaust fan (KEF-1) for that location. Clarify this situation. Reference: Section 107.2.1, IBC 2018 |
09/22/2020 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Needs Review | |
09/25/2020 | NICHOLAS ROSS | ZONING | REVIEW | Reqs Change | DP20-0147 must be approved first |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
10/19/2020 | IMONSHI1 | OUT TO CUSTOMER | Completed |