Permit Review Detail
Review Status: Completed
Review Details: RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO
Permit Number - T20CM05794
Review Name: RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/02/2020 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | ZONING REVIEW TRANSMITTAL FROM: Steve Shields Site Section Manager PROJECT: T20CM05794 8720 E Bears Path Rd New Shop, Outdoor Kitchen and Addition to Guest House TRANSMITTAL: September 2, 2020 COMMENTS: The following comments are for the purpose of applying for a variance before the Board of Adjustment (UDC Section 3.10.1). This site is located in the RX-1 zone (UDC 4.7.6). A single-family residence (SFR) is a permitted use in this zone (Table 4.8-1). See Use-Specific Standards 4.9.7.B.6, .8, & .9. 1. Based on permit T08CM02841 the existing detached living quarters has been converted to a 2nd dwelling unit. Per UDC Table 6.3-1.A: DIMENSIONAL STANDARDS FOR THE RH, SR, SH, RX-1, & RX-2 ZONES, RX-1 Zone, only one (1) dwelling unit is allowed on this parcel, a board of Adjustment for Variance is required for the second dwelling unit. 2. Per UDC Article 6.6.3.C Accessory structures shall not exceed 12 feet in height, unless attached to a principal structure. Per UDC Article 6.4.4.A Building height is the vertical distance measured from the design grade elevation to the middle (between the eave and ridge) of the highest gable of a pitched or hipped roof. That said the proposed shop building exceeds the allowed 12' height. Correct building height was not provided. 3. The minimum setback is twenty feet (20) facing each interior property line (Table 6.3-1.A).Proposed perimeter yard setback from the addition to the guest house and the shop to the west property line is 17'-0". Proposed perimeter yard setback from the proposed shop to the south property line is 15'-0" If the Board of Adjustment is approved provide a note on the plot plan stating the case number, date of approval, what was modified and if applicable conditions of approval. |
| 09/02/2020 | SSHIELD1 | ENGINEERING | REVIEW | Passed | |
| 09/02/2020 | SSHIELD1 | NPPO | REVIEW | Passed | |
| 10/19/2020 | KEN VAN KARSEN | BUILDING-RESIDENTIAL | REVIEW | Completed |