Permit Number: T20CM05673
Parcel: 14043011A

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T20CM05673
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/31/2020 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please address the following electrical plan review comments. Also provide a written response.
1. Revise the IECC calculations to reflect the currently adopted 2018.
2. Revise the NEC Code reference on the title sheet to 2017.
3. Provide a mark or identification for the ceiling mounted luminaires that correlate with the luminaire schedule.
4. Verify that the luminaires installed above the classified areas meet the requirements of NEC 513.7C.
5. Provide a note on the power plans referencing the that the wiring methods are to comply with NEC art 513.
Ref; 2018 IBC sec, 107.2.1, 2017 NEC, 2018 IECC, City of Tucson Commercial Plan Submittal Requirements, 2012 Tucson/Pima County Outdoor Lighting Code.
09/01/2020 STEVE SHIELDS ZONING REVIEW Reqs Change CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: Steve Shields
Section Manager

PROJECT: T20CM05673
New Hanger
1840 E Valencia Rd.

TRANSMITTAL DATE: September 1, 2020

DUE DATE: August 31, 2020

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

1. Zoning has reviewed the building plans for compliance with the submitted development package DP20-0156. As size and heights were not provided on the DP zoning cannot determine if the building plans match the DP. Zoning cannot approve the building plans until PDSD Commercial Plans reviewers have approved the building plans.

2. The Civil sheets provided in the building plan either need to be the stamped approved development package sheets, marked for reference only or removed from the building plans.

If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
09/01/2020 DTRAMME1 ENGINEERING REVIEW Passed
09/03/2020 JPEELDA1 FIRE REVIEW Approved
09/03/2020 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. The International Plumbing Code, 2018, is the controlling code for this structure, not the Uniform Plumbing Code. Reference: Section 101.2, IPC 2018
2. Verify the existence of the 8" sewer shown on sheet S1.E. Show the inverts and slope of the new building sewer and show how the connection is to be made to the existing (?) 8" sewer. Reference: Section 107.2.1 and 107.2.6, IBC 2018.
3. Provide third-party listing and material standards for all plumbing fixtures being installed. Reference: Sections 303.4 and 402, IPC 2018.
4. Provide the minimum plumbing facilities required by Table 2902.1, IBC 2018, for storage occupancy.
5. Provide specifications for the shower valve. Reference: Section 412.3, IPC 2018.
6. Provide the model number and operating characteristics of the specified water heater. Verify that the unit can provide sufficient tempered or hot water for the shower. Note that the cold & hot water isometric does not show hot water being supplied to the shower. Reference: Section 107.2.1, IBC 2018 and Section 607.1, IPC 2018.
7. Provide a metering faucet for the lavatory, dispensing a maximum of 0.25 gallons per metering cycle. Verify that the faucet cycle will last for at least 10-seconds. Reference: Section 419.6, IPC 2018, as amended by the City of Tucson and Section 606.4, ICC/ANSI A117.1-09.
8. Provide tempered water for the lavatory using an approved device conforming to ASSE 1070. Reference: Sections 416.5 and 607.1.2, IPC 2018.
9. Provide calculations showing how the water supply piping has been sized. Reference: Sections 604.1 and 604.3, IPC 2018.
10. Provide a full-open valve for the water service at the building entrance. Reference: Section 606.1(2), IPC 2018.
11. A note on sheet M1.0 calls for HVAC condensate drains to be "plumbed to the sanitary sewer system." Show how this will be done. Reference: Section 802.1.5, IPC 2018.
12. Revise the venting configuration of the restroom to one of the methods described in Chapter 9, IPC 2018.
09/03/2020 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Demonstrate energy code compliance for the building envelope using calculations based on the current code. Provide sufficient detail on the drawings to evaluate the energy compliance of the building envelope. As a minimum, the information shall include U-factors of the envelope systems and fenestration components, along with the R-values of the insulation and the SHGC for the fenestration. Reference: Sections C101.5, C103.2, C303, and C401.2, International Energy Conservation Code 2018.
2. Show how one of the "Additional Efficiency Package Options" (C406, IECC 2018) is to be accomplished. Reference: Section C401.2, IECC 2018.
3. Provide heating and cooling load calculations to justify the heating/cooling capacities of the specified HVAC units. Reference: Section C403.1.1 and C403.3.1, IECC 2018.
4. Two outdoor units and two indoor units are shown on the mechanical plan but only one outdoor unit and one indoor unit are specified. Provide specifications for all units. Show that the units are being installed per the manufacturer's instructions. Reference: Sections 301 and 304.1, IMC 2018.
5. Show the size, routing, and termination of the condensate drains. Reference: Section 107.2.1, IBC 2018.
6. Ventilation is required and must be provided whenever the space is occupied. Reference: Sections 401.2 and 401.3, IMC 2018.
7. Secure the refrigerant circuit access ports of the condensing units to prevent unauthorized access. Reference: Section 1101.10, IMC 2018.
09/03/2020 ROBERT SHERRY WATER REVIEW Reqs Change 1. Show the location of the proposed water meter, backflow preventer, and the water service pipe on a site plan. Reference: Section 107.2.1 and 107.2.6, IBC 2018.
2. An 8" water main serving a fire hydrant appears to run below the proposed hangar location. Verify its existence and relocate it if needed.
09/25/2020 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Sheet C1.0 (Proposed Building Areas); Sheet C1.1 (Code Analysis): The Proposed Building Area indicates 4817 SF, while the Code Analysis indicates 4225 SF. Please coordinate.
2. Sheet C1.1; Code Analysis (Allowable Area): Please indicate the allowable area for an S-1 Occupancy Classification with IIB Construction Type per the IBC Table 506.2.
3. Sheet C1.1; Code Analysis (Occupant Load): Please provide the building occupant load.
4. Sheet S1.0 (Foundation Plan); Sheet AB-1 (Metal Building Drawings): Please verify the anchor bolt locations match on these two sets of drawings. The main rigid frame columns on the east wall have a 1'-2" dimension to the centerline on the Foundation Plan, but 8" on Sheet AB-1. Please coordinate all dimensions on these sheets.
5. Sheet S1.2; Bath/Toilet Elevation A: Please revise the reference in Keynote 6 shown on the Elevation to 5 at the grab bars.
6. Sheet S1.6; Detail 10: Please indicate the height of the railing above finish floor. In addition, indicate how the railing posts are spaced on the plan and how they are connected at their base. Please provide a new detail for that condition.
7. Sheet G1.0; General Structural Notes (Foundations): Please indicate the maximum allowable soil bearing pressure in the Foundation notes per the geotechnical report.
8. Sheet AB-1; Metal Building Drawings: The Anchor Bolt Setting Plan indicates anchor bolts on the east wall. Please verify.
9. Sheets AB-1, E-01, and E-06; Plans: Please provide north arrows on those sheets.
10. Metal Building Drawings: Please indicate wall bracing as required on the metal building elevations (see calculations).
11. General: Please provide a Special Inspections Certificate with Parts A and B completed. This form may be found at www.tucsonaz.gov/PDSD.
12. General: Please provide written responses to all review comments.
09/25/2020 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Needs Review

Final Status

Task End Date Reviewer's Name Type of Review Description
10/07/2020 IMONSHI1 OUT TO CUSTOMER Completed