Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Permit Number - T20CM05670
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/03/2020 | JPEELDA1 | FIRE | REVIEW | Approved | |
09/08/2020 | EHAMBLI1 | OIP | REVIEW | Passed | |
09/08/2020 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Reqs Change | T20CM05670 1) Provide a seperate Development Package for this submittal. Submittal to include an update to the Master Developed Area Detention/Retention requirments for the watershed in which this project is located to verify that no detention/retention triggers are being met 2) Reference City of Tucson Administrative Manual section 2-06 3) Once the development package has been approved, Engineering can approve the building plans John Van Winkle, P.E. John.VanWinkle@tucsonaz.gov |
09/08/2020 | ELISA HAMBLIN | ZONING | REVIEW | Reqs Change | T20CM05670 All City-owned properties are subject to archaeological review per City administrative directives. Please contact Jodie Brown at Jodie.Brown@tucsonaz.gov to determine if additional documentation is required for this site. Provide letter or email from Jodie with next plan submittal. See Engineering comments for other applicable site requirements. Elisa Hamblin, AICP Principal Planner Elisa.Hamblin@tucsonaz.gov |
09/24/2020 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
09/24/2020 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet CS1.101; General Structural Notes (Geotechnical): This note indicates a geotechnical report was not developed for this project. However, a geotechnical report is included in the drawings. Please coordinate. 2. Sheet SS0.001; General Structural Notes (Foundations): Please indicate the Geotechnical Report Number and recommendations in this note. 3. Sheet SS1.002 (Roof Framing Plan); Detail 206/SS5.201: Detail 206/SS5.201 was not located on the Roof Framing Plan on Sheet SS1.002. Please verify. 4. General: Please provide a Special Inspections Certificate with Parts A and B completed. 5. General: Please provide written responses to all review comments. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
10/06/2020 | PCAMARE1 | OUT TO CUSTOMER | Completed |