Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Permit Number - T20CM05624
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/03/2020 | JPEELDA1 | FIRE | REVIEW | Approved | |
| 09/04/2020 | NROSS1 | OIP | REVIEW | Passed | |
| 09/04/2020 | NICHOLAS ROSS | ZONING | REVIEW | Reqs Change | An updated Development Package is required before Zoning can approve building plans. |
| 09/08/2020 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Needs Review | |
| 09/08/2020 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet T.1.0; Code Review (Plumbing Fixtures): The required plumbing fixtures must be calculated using the IBC Section 2902.1.1. For multiple occupancy classifications, divide the number of males/females in each occupancy classification by the Table 2902.1 associated number for that occupancy classification, then sum those numbers to get the total water closets required and the total lavatories required (round up). 2. Sheet T.1.0; Code Review (Area): The sum of the retail (7257 SF) + storage (7468 SF) + office addition (1575 SF) should total 16,300 SF. Please verify. 3. Sheet T.1.0; Code Review (Actual/Allowable Area): Use the IBC Table 506.2 to determine the allowable area factors for each occupancy classification (B=36,000 SF/M=36,000 SF/S-1=36,000 SF). Follow the IBC Section 508.4.2 using the actual SF of each occupancy classification divided by the allowable SF of each occupancy classification. The sum of those numbers must not exceed 1. Show those calculations on the drawings. 4. Sheet T.1.0; Code Review (Allowable Building Height/Allowable Number of Stories): Please use the IBC Tables 504.3 and 504.4 for the allowable number of building height and stories (use only the most restrictive occupancy classification). 5. Sheet A.1.0; Floor Plan: Please indicate on this plan what the heavy dashed wall line between the new office addition and the existing pool equipment, parts, and accessories are signifies. Please indicate if this is a fire resistant rated wall, the section of the IBC Code that requires a fire resistant rated wall, the required fire resistance rating, and the U.L. Listing Number for that wall assembly. Provide a section or detail through that wall as required. 6. Sheet A.1.0; Floor Plan: Please verify the hazardous materials indicated on this plan do not exceed the limits set in the IBC Tables 307.1(1) and 307.1(2). Indicate on the drawings the allowable quantities/actual quantities of the various materials. 7. Sheet A.1.0; Floor Plan: The new interior partitions in the addition are indicated by Keynote 3. Please revise that Keynote reference. 8. Sheet A.2.0; Reflected Ceiling Plan: Please indicate the exit lighting on this plan, or reference a sheet that has that information. 9. General: Please provide structural calculations for the new addition, general notes, details, and sections as required. 10. General: Please provide written responses to all review comments. |
| 09/16/2020 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Reqs Change | T20CM05624 1) Refer to Zoning Comment, a separate development package submittal and review is required. For that Development package show the following 2) Provide waste stream calculations on plans per TSM section 8-01.8.0 showing that the existing service is sufficient for the proposed expansion. Otherwise show how the required service will be provided 3) Ensure that roof drains, from the new buildings, scupper underneath sidewalks as needed. Reference COT Technical Standards Manual (TSM) section 7-01.4.1.e 4) Include all standard applicable notes/requirments found in the COT Administrative Manual (AM) section 2-06 John Van Winkle, P.E. John.VanWinkle@tucsonaz.gov |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 10/05/2020 | IMONSHI1 | OUT TO CUSTOMER | Completed |