Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/21/2020 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Approved | |
09/23/2020 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | Comment not addressed. [Initial comment: Provide construction documents that are complete and clearly indicate the extent of the proposed mechanical work. Reference: Section 107.2.1, IBC 2018.] |
09/23/2020 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Comment not addressed. [Initial comment: Provide construction documents that are complete and clearly indicate the extent of the proposed plumbing work. Reference: Section 107.2.1, IBC 2018.] |
10/07/2020 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. Provide complete electrical floor plans. Include; (a) Designated branch circuits and panel for all power devices and lighting. NEC 408.4. (b) Complete panel schedule including load calculations for increased load as the result of the proposed electrical installations. (c) Clearly indicate what is new and what is existing on the plans. (d) Provide compliance with the 2018 IECC for the lighting. Ref; 2018 IBC 107.2.1, 2017 NEC. |