Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T20CM05125
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/10/2020 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
08/10/2020 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Clarify the scope of work. Drawing A1 through A3 do not appear to relate to the submitted structural drawings. 2. Provide plans sealed by an Arizona Registrant. Reference: Arizona Revised Statutes 32-125, Board of Technical Registration Rules R4-30-304 |
08/10/2020 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Clarify the scope of work. Drawing A1 through A3 do not appear to relate to the submitted structural drawings. 2. Provide plans sealed by an Arizona Registrant. Reference: Arizona Revised Statutes 32-125, Board of Technical Registration Rules R4-30-304 |
08/10/2020 | LOREN MAKUS | ENGINEERING | REVIEW | Passed | |
08/10/2020 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheets A1, A2, and A3: Please provide construction documents prepared by a registered design professional per the IBC Section 107.1. 2. Sheet A1; Floor Plan: Please indicate the new mezzanine on this floor plan. 3. Sheet A2; Plans: Please identify each plan as either Building, Electrical, or Mechanical. 4. Sheet A3; Plans: Please identify each plan as either Floor Plan or Mechanical Plan. 5. Sheet A3; Specifications (Walls): The Specifications indicate new 2x6 metal studs at 16" o.c., while the Floor Plan indicates 2x4 at 16" o.c. metal studs. Please coordinate. 6. Sheet A3; Specifications (Walls): Since these are metal studs, indicate the gauge of those studs in the Specifications (Wall Section indicates 20 gauge). 7. Sheet A3; Floor Plan: Please indicate dimensions on the Floor Plan to locate all new walls. 8. Sheet A3; Specifications: Please revise the NEC to the 2017 Edition. 9. Sheet A3; Wall Section: Please indicate on the Floor Plan where this Wall Elevation/Section is cut. 10. Sheet M1; Mezzanine Notes (Foundation): Please provide structural calculations to verify existing/new foundations are adequate to support the new mezzanine per Mezzanine Notes 2. 11. Sheet M2; Plan Layouts: Please provide north arrows on these plans. 12. Sheet M3; Floor Plan Layout: Please provide a north arrow on this plan. 13. Sheet M3; Floor Plan Layout: A note at the upper right of this plan indicates to see detail on Sheet M1 of M1 for a beam connection. Please revise the detail reference. 14. General: Please provide a Special Inspection Certificate with Parts A and B completed. This form may be found at www.tucsonaz.gov/PDSD. 15. General: Please provide a project valuation (labor + materials). 16. General: Please provide written responses to all review comments. |
08/10/2020 | ROBERT SHERRY | WATER | REVIEW | Reqs Change | Clarify the scope of work. |
08/10/2020 | JPEELDA1 | FIRE | REVIEW | Approved | |
08/18/2020 | JGARCIA1 | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Clarify the scope of work. Drawing A1 through A3 do not appear to relate to the submitted structural drawings. 2. Provide plans sealed by an Arizona Registrant. Reference: Arizona Revised Statutes 32-125, Board of Technical Registration Rules R4-30-304 |
08/21/2020 | STEVE SHIELDS | ZONING | REVIEW | Approved |