Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/26/2020 | LOREN MAKUS | ENGINEERING | REVIEW | Passed | |
06/26/2020 | ELISA HAMBLIN | ZONING | REVIEW | Reqs Change | FROM: Elisa Hamblin, AICP PDSD Zoning Review PROJECT: T20CM04010; Elevator Work Building Plans (1st Review) 345 E Congress St. TRANSMITTAL DATE: June 26, 2020 DUE DATE: June 22, 2020 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review comments were addressed. 1. COMMENT: Zoning has reviewed the building plans but cannot approve them at this time. As an exterior alteration in the Rio Neuvo Area, RNA design review is required. Please contact Maria Gayosso at Maria.Gayosso@tucsonaz.gov for application information. You may also find additional information online here: https://www.tucsonaz.gov/pdsd/special-districts#RNA 2. COMMENT: Once the plans have been reviewed and approved as part of the RNA process, the building plans can be approved by zoning. If you have any questions about this transmittal, please contact me at Elisa.Hamblin@tucsonaz.gov or (520) 837-4966. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: building plans and approval letter for RNA process. |
06/30/2020 | JPEELDA1 | FIRE | REVIEW | Approved | |
07/02/2020 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet A0.0; Sheet Index: The Sheet Index indicates a Sheet A1.1. This sheet was not included in this submittal. Please provide. 2. Sheet A3.0; Sections 6 and 7: Please indicate the 8" steel joist gauge on these sections or in a note. 3. Sheet A3.0; Section 2: Please indicate the depth and gauge of the double lintel over the door. 4. Sheet A3.0; Sections 6, 8, and 10: Please indicate the 3 5/8" metal wall stud gauge. 5. Sheet A3.0; Section 7: Please indicate the steel angle size and the expansion anchor size, length, and spacing. Is the angle welded to the wall studs? Please indicate. 6. Sheet A3.0; Section 10: Please indicate the steel angle size and the expansion anchor size, length, and spacing. Please indicate the distance of the angle below the concrete slab. Is the angle welded to the wall studs? Please indicate. 7. General: Are any Special Inspections required for this project? If so, please provide a Special Inspection Certificate with Parts A and B completed. This form may be found at www.tucsonaz.gov/PDSD. 8. General: Is this new enclosure have an automatic sprinkler system? Please verify. 9. General: Please provide written responses to all review comments. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
10/13/2020 | PC_TGUTHEI1 | OUT TO CUSTOMER | Passed |
10/13/2020 | PC_TGUTHEI1 | APPROVAL SHELF | Passed |