Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T20CM03684
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 06/16/2020 | JPEELDA1 | FIRE | REVIEW | Approved | |
| 06/18/2020 | ALEXANDRA HINES | ZONING | REVIEW | Approved | |
| 06/18/2020 | AHINES2 | ENGINEERING | REVIEW | Passed | |
| 06/22/2020 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet A1; Code Review: It appears from the Floor Plan the Occupancy Classification for this space would be a Factory F-1 where signs are manufactured. Please verify. 2. Sheet A1; Code Review: Please revise the Code Review (Occupancy Group, Occupant Load, and Plumbing Fixtures) due to the change of the Occupancy Classification (Comment 1). 3. Sheet A1; Code Review: The Occupant Load indicates 35, but the calculation indicates 24. Please coordinate. 4. Sheet A3; Floor Plan: The Cover Sheet A1 indicates two exits are provided. Per the IBC Section 1007.1.1, the exits in a non-sprinklered building must be placed a distance apart not less than 1/2 the length of the maximum overall diagonal dimension of the building. These exits do not appear to meet that requirement. Please verify. 5. Sheet A3; Floor Plan: A single exit may be used if the maximum common path of egress travel distance does not exceed the value listed in Table 1006.2.1 (75'). If the path from any space in this tenant space to the exit exceeds that distance, a second exit must be provided. Please verify and indicate that information on the plan. 6. Sheet A6; Detail 5: A note at the bottom of this partition references Detail 6 on Sheet A6. Please add that detail. 7. General: Please provide a valuation for this project. 8. General: Please provide written responses to all review comments. |
| 06/22/2020 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
| 06/23/2020 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Completed | |
| 06/23/2020 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please revise the IECC lighting calculations to the current 2018. |
| 06/23/2020 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 06/23/2020 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Provide an approved vacuum relief valve for the scheduled bottom-fed water heater that is located above the fixture outlets. Reference: Section 504.2, IPC 2018. |