Permit Number: T20CM03313
Parcel: 13327001C

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T20CM03313
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/01/2020 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Approved
06/01/2020 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Provide labels for the existing rooftop units to coordinate the ventilation calculations (called "Outside Cooling Calculations" on sheet M1.0). Reference: Section 107.2.1, IBC 2018.
2. Show the balancing data for the supply diffusers on the mechanical plan. Reference: Section 107.2.1, IBC 2018.
06/01/2020 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. If the shower does not have a pre-fabricated receptor, provide details to show that the construction of the receptor complies with the requirements of Section 421.5, IPC 2018. (Note: shower is labeled as a mop sink on P1.0)
2. Provide shower valves that comply with the requirements of Section 412.3 and 424.5, IPC 2018.
06/01/2020 MARTIN BROWN FIRE REVIEW Approved
06/01/2020 ROBERT SHERRY WATER REVIEW Completed
06/03/2020 SAMUEL ROGERS ZONING REVIEW Approved
06/03/2020 SROGERS2 ENGINEERING REVIEW Passed
06/05/2020 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Sheet TS1; Code Review: Phase II and Phase III are listed in the Code Review. Will these be completed under separate permits? Please indicate on the drawings.
2. Sheet TS1; Code Review: Please provide the calculations on this sheet for the plumbing fixture requirements per the IBC Section 2902.1.1.
3. Sheet TS1; Code Review: Plumbing fixture requirements for Phases II and III must be calculated for the future permits per the IBC Section 2902.1.1.
4. Sheet A1.0; Floor Plan: Please indicate on this sheet that work (as indicated) may not be performed on an portions of Phase II or III under this permit.
5. Sheet A1.0; Floor Plan: Please indicate the new partition walls stud size and spacing. Provide a detail for bracing all new partitions that do not extend to the roof deck.
6. Sheet A1.0; Floor Plan: Is the shower unit in Phase II? Please verify.
7. Sheet A2.0; Reflected Ceiling Plan: Please indicate the exit lights on this plan.
8. General: Please provide elevations for the grab bars in the restrooms per the ICC/ANSI Figures 604.5.1 and 604.5.2.
9. General: Please provide written responses to all review comments.
06/05/2020 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed