Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T20CM03066
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
07/28/2020 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet 2-GI003; Allowable Building Area Table: The F-1 Section and the A-3 Section do no indicate 'Fire Sprinklered'. Please verify. 2. Sheet 2-GI003; Occupancy Table: The 'Maximum Floor Area Allowances' references Table 1004.1.2. Please revise that reference to the 2018 IBC Table number. 3. Sheet 2-GI003; Allowable Building Area and Height Table: Per the IBC Section 506.2.4, the allowable area is for each story of a two story building. Please verify. 4. Sheet 2-GI003; Minimum Plumbing Facilities Table: The table indicates no plumbing fixtures are required for the H-2 area. Please verify and reference Sheet 2-GI005 for the location of those units. 5. Sheet 2-GI005; Life Safety Plan: Some of the Occupant Load Factors (OLF) indicated on this plan do not match the factors used on the Occupancy Table on Sheet 2-GI003. Please verify. 6. Sheet 2-GI006; Life Safety Plan: Because the exit access stairways are unenclosed, the exit access travel distance must include the distance down the stairs and to the exits per the IBC Section 1017.3.1. Please verify the distances. 7. Sheet 2-GI006; Life Safety Plan: The Occupant Load Factor (OLF) on this plan does not match the factor used on the Occupancy Table on Sheet 2-GI003. Please verify. 8. Sheet 2-SF101; Roof Framing Plan: A joist on the northeast portion of the roof (next to Grid Line 11 and between Grids 14 and 16) does not have a joist reference. Please verify. 9. Sheet 2-SF101; Roof Framing Plan: Joists on the southwest portion of the roof (next to Grid Line 13 and between Grids 14 and 16 and between Grids 16 and E14) do not have a joist reference. Please verify. 10. General: Is there no Roof Framing Plan for the new hangar because it is a metal building designed and detailed by a separate manufacturer? Please verify. 11. General: Please provide a Special Inspection Certificate with Parts A and B completed. This form may be found at www.tucsonaz.gov/PDSD. 12. Sheet 2-AR102; First Floor Plan: At the Enlarged Plan Break Room 121, please clear up the section call-out. It is not legible. 13. Sheet 2-AR104; Floor Plan: It does not appear all interior partitions are assigned a Partition Type (Student Services 158, Conference 166, etc.). Please verify. 14. Sheet 2-AR106; Reflected Ceiling Plan: Please indicate all exit lights on this plan, or reference Electrical for that information. 15. Sheet 2-AR107; Reflected Ceiling Plan: Please indicate all exit lights on this plan, or reference Electrical for that information. 16. Sheet 2-AR108; Reflected Ceiling Plan: Please indicate all exit lights on this plan, or reference Electrical for that information. 17. Sheet 2-AR109; General Notes: Note G indicates suspended equipment racks Detail 11/2-SJ501. These should be indicated as suspended pipe/utility racks. Please verify. 18. Sheet 2-AR109; Framing Plan: The plan title indicates 'Preliminary PEMB Roof Framing Plan'. Please add a note on this sheet indicating when this sheet will remove the "Preliminary" in the title. 19. Sheet 2-AR109: Please add a north arrow to this plan. 20. Sheet 2-AR110; Framing Plan: The plan title indicates 'Preliminary PEMB Framing Plan'. Please add a note on this sheet indicating when this sheet will remove the "Preliminary" in the title. 21. Sheet 2-AR110: Please add a north arrow to this plan. 22. Sheet 2-AR602; Door Schedule: Please add a note referencing the location of the Hardware Types listed in the Door Schedule. 23. General: Please provide written responses to all review comments. |
08/12/2020 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Verify that the specified sensor faucet for the public lavatories has an automatic time-out so that it will dispense a maximum of 0.25 gallons per metering cycle. Reference: Section 419.6, IPC 2018, as amended by the City of Tucson and Section 606.4, ICC/ANSI A117.1-09. 2. Verify that the pipe sizes called out for the flush valves will not result in water velocities greater than that recommended by the pipe manufacturer (e.g. limit the water velocity to less than 8 FPS for copper piping). At a minimum design flow rate of 25 GPM for a siphonic, flush-valve water closet, a 1" Type L copper pipe has a flow velocity of 9.7 FPS. Reference: Table 604.3, IPC 2018. 3. Provide roof drainage calculations and plans. Provide overflow protection for the roof. Reference: Sections 1101, 1106 and 1108, IPC 2018. |
08/12/2020 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Show the required minimum R-values for wall and roof insulation and the maximum U-factors and Solar Heat Gain Coefficients (SHGC) for the fenestration and doors on the architectural drawings to coordinate with the component descriptions in the COMcheck Envelope Compliance Certificate. Reference: Section C103.2, IECC 2018. 2. Provide heating and cooling load calculations to justify the heating/cooling capacities of the specified HVAC units. Reference: Section C403.1.1 and C403.3.1, IECC 2018. 3. Coordinate the fan schedule with the hangar air flow and controls diagram. The diagram has mislabeled fans. Reference: Section 107.2.1, IBC 2018. 4. Show the size, routing, and termination of the condensate drains. Reference: Sections 307.2.1 and 307.2.3, IMC 2018 as amended by the City of Tucson. 5. The City of Tucson did not adopt ASHRAE Standard 62.1 for ventilation calculations and the 2018 IMC only references the ASHRAE Standard for the purpose of calculating the system ventilation efficiency (Ev). Provide calculations to show that the ventilation system is sized in accordance with Section 403.3, IMC 2018. 6. Provide information on the sequence of operation for the restroom exhaust fans to show that all of the air supplied to the restrooms will be exhausted. Reference: Section 403.2.1 (4), IMC 2018. |
08/13/2020 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | PDSD TRANSMITTAL FROM: Steve Shields Section Manager PROJECT: Pima Community College - Aviation Technology Center Expansion Building Plan T20CM03066 TRANSMITTAL DATE: August 13, 2020 1. Zoning has reviewed the building plans for compliance with submitted development package DP20-0103. While the building plans are consistent with the submitted DP as it relates to the zoning review purview of the building footprint, building height, square footage, site conditions etc., zoning cannot approve the building plans until the DP has been approved and all PDSD Commercial Plans reviewers have approved the building plans. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 |
08/31/2020 | STANTEC | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | ELECTRICAL COMMENTS Sheets 2-EL101 and 2-EL102 1. The circuit for the elevator pit shall have only the light in the pit on that circuit per 2017 NEC Art. 620.24. 2. Provide the location of the elevator machine room/machine space and provide a lighting circuit as required by 2017 NEC Art. 620.23. Sheets 2-EP601 and 2-EP602 1. Clearly identify all circuits that supply power to exit/egress lighting unit equipment at the distribution board as required by 2017 NEC Art. 700.12(F). 2. Clearly identify existing loads being moved to the new panel and provide all the information required to verify code compliance. Sheet 2-EP701 1. Provide the primary disconnect requirements for the transformers as required by 2017 NEC Art. 450.14. 2. Verify the ratings of Panels LP411, LP412, LP413, LP421, and LP422 to verify compliance with 2017 NEC Art. 110.9 and 110.10. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
08/31/2020 | JGARCIA1 | APPROVAL SHELF | Completed |
08/31/2020 | JGARCIA1 | OUT TO CUSTOMER | Completed |
08/31/2020 | JGARCIA1 | REJECT SHELF | Completed |