Permit Number: T20CM02923
Parcel: 11615087D

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T20CM02923
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/11/2020 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed
05/11/2020 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Provide structural calculations and details to show how the water-source heat pump units in excess of 200-pounds are to be connected to the building structure. Reference: Section 302.1, IMC 2018.
2. Provide heating and cooling load calculations to justify the heating/cooling capacities of the specified water-source heat pump units. Reference: Section C403.1.1 and C403.3.1, IECC 2018.
05/11/2020 MARTIN BROWN FIRE REVIEW Approved
05/11/2020 ROBERT SHERRY WATER REVIEW Completed
05/12/2020 ALEXANDRA HINES ZONING REVIEW Approved
05/12/2020 AHINES2 ENGINEERING REVIEW Passed
05/12/2020 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Sheet g2.0; Second Floor Plan: It appears from the plan a single exit (rated stairwell) is being provided for this space. Per the IBC Table 1006.2.1, a sprinklered B occupancy with a maximum occupant load of 49 allows a maximum common path of egress travel distance of 100 feet. The distance indicated on the plan is greater than the allowable for a single exit. Please verify.
2. Sheet g2.0; Second Floor Plan: In the corridor south of Office 218, Office 219, and the stair, an interior wall is indicated at the west end. In order not to consider this a dead end corridor, occupants would be required to exit through the Reception 203 area. This would require exit lighting per the IBC Section 1013. Please verify and place information on the drawing.
3. Sheet a2.0; Second Floor Reflected Ceiling Plan: Please indicate exit lighting on this plan, or add a reference note indicating the location of that lighting.
4. General: Please provide written responses to all review comments.
05/12/2020 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
05/13/2020 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please provide complete compliance with the 2018 IECC for the lighting.