Permit Review Detail
Review Status: Completed
Review Details: 3RD PARTY REVIEW - COMMERCIAL
Permit Number - T20CM02083
Review Name: 3RD PARTY REVIEW - COMMERCIAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/08/2020 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | PDSD TRANSMITTAL FROM: Steve Shields Section Manager PROJECT: TEP Operations Center - Foundation Only T20CM02083 Foundation Plan (1st Review) TRANSMITTAL DATE: June 8, 2020 1. Zoning has reviewed the foundation plan for compliance with the approved development package DP18-0088. DP18-0088 sheet C01, under BUILDING KEYNOTE 11 FIELD OPERATION CENTER BLDG. (NEW ARCH. BLDG.#1. The building shown on the DP and labeled with keynote 11 is a long rectangular shaped building where as this foundation plans shows a square building, clarify the difference. A revision to the DP maybe required. 2. Zoning cannot approve the building plans until PDSD Commercial Plans reviewers have approved the building plans. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 |
06/09/2020 | ROBERT SHERRY | WATER | REVIEW | Passed | |
07/06/2020 | LOREN MAKUS | ENGINEERING | REVIEW | Approved | |
07/06/2020 | LMAKUS1 | LANDFILL | REVIEW | Passed | Not required. Greater than 500 feet from landfill. |
07/07/2020 | JPEELDA1 | FIRE | REVIEW | Approved | |
08/25/2020 | STANTEC | 3RD PARTY REVIEW-COMMERCIAL | AT 3RD PARTY OFFICE | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
08/25/2020 | JGARCIA1 | APPROVAL SHELF | Completed |
08/25/2020 | JGARCIA1 | OUT TO CUSTOMER | Completed |
08/25/2020 | JGARCIA1 | REJECT SHELF | Completed |