Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T20CM00644
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/26/2020 | IMONSHI1 | ZONING | REVIEW | Approved | |
| 02/26/2020 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 02/26/2020 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Approved | |
| 03/05/2020 | RMCCOY1 | BUILDING-COMMERCIAL | REVIEW | Approved | |
| 03/05/2020 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. Ref; Line diagrams. Provide voltage, ampere, phase, AIC rating of the existing service equipment. 2. Verify that the DG Disconnect meets the requirements per NEC 690.13 for ratings. 3. Provide a detail showing the inverter and associated equipment mounting. If pole mounted, include distances above grade. If the inverter is mounted at a not readily accessible location, provide compliance with NEC 705.70. 4. Verify that the bus in the service equipment at the exact point of interconnection is factory marked "TAP". If not, provide a letter or document from the manufacturer of the service equipment stating that the line side tap as proposed will in no way compromise the listing or the performance of the equipment, signed by a person that has the authority by that manufacturer to make such a statement. Include all hardware used with a detail. Otherwise, provide for a field evaluation by an NRTL or qualified agency to be performed after the proposed tap is complete to re-certify and maintain the listing of the equipment. NEC 110.3, 230.66. 5. Ref; Plan Sheet 11 of 13. show the location and name of the breaker panel and branch circuit utilized for the new exterior lighting. Verify that this panel has available space to accommodate an additional branch circuit and capacity for the additional load. Ref; 2018 IBC 107.2.1, 2017 NEC, City of Tucson Commercial Plan Submittal requirements. |