Review Date Reviewer's Name Type of Review Description Status Comments
02/03/2020 MARTIN BROWN FIRE REVIEW Approved
02/10/2020 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change Plumbing general note #6 calls for all sewer piping to run at 1/8" per 12" slope unless noted otherwise. Horizontal sewer pipes less than 3" require a minimum slope of ΒΌ" per 12".
02/10/2020 ROBERT SHERRY WATER REVIEW Completed
02/13/2020 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Sheet G003; Code Diagram 1 (Garage): A plan note indicates '22,991 NSF open parking S-2', followed by '23,632 NSF covered'. This would indicate more covered parking than there is actual parking. Please clarify.
2. Sheet G003; Floor Plans: Please indicate the means of egress and the exit access travel distances on the plans per the IBC Section 107.2.3, and verify the maximum distance indicated on Sheet G002 (195') is the worst case.
3. Sheet A-A100.0; Parking Floor Plan: The Sheet Title indicates Level 0, while the Floor Plan Title indicates Level 1-P. Please verify.
4. Sheets A-A120 and A-A121.1; Reflected Ceiling Plans: Please add a Key Plan to these sheets.
5. Sheets A-A150, A-A151, etc.; Slab Plans: Please add a Key Plan to these sheets.
6. Sheet A-A501; Wall Type: Please indicate a U.L. Listing Number on Wall Types D1, D2, and D3.
7. Sheet A-A501; Wall Type B4: The one hour fire resistance rating provides a U.L. Listing Number, but the Wall Title indicates a two hour wall. Please verify.
8. General: Are there any Special Inspections required for Site Preparation, Excavation, etc., that should be included on the Special Inspection Certificate? Please verify and add as required.
9. General: Please provide written responses to all review comments.
02/19/2020 ROBERT SHERRY WATER REVIEW Completed
02/20/2020 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change Provide calculations to show how natural ventilation has been provided for both garage levels. Reference: Section 402.2, IMC 2018.
02/24/2020 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please address the following electrical plan review comments. Also provide a written response.
1. Provide complete compliance with the Tucson/Pima County Outdoor Lighting Code for the exterior Lighting.
2. Please submit a power, systems, and lighting plan for level 1 and 2 of the parking garage.
3. Provide a grounding electrode system for the parking garage. NEC 250.32
Ref; 2018 IBC 107.2.1, 2017 NEC, City of Tucson Commercial Plan Submittal requirements, 2012 Tucson/Pima County Outdoor Lighting Code.
02/25/2020 SAMUEL ROGERS ZONING REVIEW Reqs Change FROM: Samuel Rogers
PDSD Zoning Review Section

PROJECT: T20CM00314
Benedictine Monastery Commercial Building Plan (1st Review)
800 N Country Club Rd.

TRANSMITTAL DATE: 2/25/20

DUE DATE: 2/24/20

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.


01. COMMENT: Zoning has reviewed the building plans for compliance with the Development Package DP19-0165. The plans appear to match the building heights, footprint, square footage, and locations on the Development Package. All other commercial reviewers must approve the plans before zoning can approve.



If you have any questions about this transmittal, Contact Samuel Rogers at (520) 837-6932 or at Samuel.Rogers@tucsonaz.gov or contact Steve Shields at (520) 837-4956 or email Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised Building Plans
03/02/2020 JOHN VAN WINKLE ENGINEERING REVIEW Reqs Change 1) Once all oustanding commercial reviews are complete Engineering will conduct a final review of the building plans for consistency against the approved Development Package
2) Please update the plan set to include the approved version of the Development Package
3) Ensure that all roof drains scupper under pedestrian circulation areas

Final Status

Task End Date Reviewer's Name Type of Review Description
04/07/2020 KROBLES1 OUT TO CUSTOMER Completed