| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/03/2020 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 02/11/2020 | IMONSHI1 | ZONING | REVIEW | Reqs Change | PDSD TRANSMITTAL FROM: Iman Monshizadeh PDSD Zoning Review Section PROJECT: Taco Giro Enclose Porch T20CM00071 Building Plan (2nd Review) TRANSMITTAL DATE: February 11th, 2020 1. The building plans have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. According to a previously approved site plan from 2000, the outside seating area with chairs and tables is labeled as a garden, not a dining area. Provide a previously approved (stamped by the PDSD) site plan that shows that area approved as dining area. Zoning will approve once this issue is resolved. If you have any questions about this transmittal, please contact Iman Monshizadeh at Iman.Monshizadeh@tucsonaz.gov or by phone at 520-837-4082, or contact Steve.Shields@tucsonaz.gov or (520) 837-4956 |
| 02/18/2020 | RMCCOY1 | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Provide a mechanical plan for the 2-mini split systems. Specify heating and cooling loads for determining the sizing of the new HVAC equipment. IECC C403.1.1. 2. Provide equipment specifications and performance ratings for the new mechanical equipment. IECC C403.3.2. 3. Specify how power will be brought to the new HVAC equipment. NEC 110.2. |
| 02/18/2020 | RMCCOY1 | ELECTRICAL-COMMERCIAL | REVIEW | Passed | |
| 02/18/2020 | RMCCOY1 | WATER | REVIEW | Passed | |
| 02/18/2020 | RMCCOY1 | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. The addition is required to comply with the 2018 International Energy Conservation code. Please state how the new enclosed dining area will be made to comply with section C502.2 of the IECC for new construction; the addition alone is required to comply with the code. C502.2. 2. Keynote #6 states NEW DOOR, SEE WINDOW AND DOOR SCHEDULE; however, there is not door or window schedule included in the plans. IBC 107.2.1. 3. Provide construction details of the storefront window assembly attachment to the roof/ceiling and floor. IBC 107.2.1. |
| 02/18/2020 | RMCCOY1 | PLUMBING-COMMERCIAL | REVIEW | Passed |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 01/24/2020 | ANY | REJECT SHELF | RECEIVED |