Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan Review Detail
Review Status: Completed
Review Details: PRESUBMITTAL MEETING
Plan Number - T19PRE0211
Review Name: PRESUBMITTAL MEETING
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
11/15/2019 | ANDREW CONNOR | LANDSCAPE | REVIEW | Completed | Indicate graphically, where possible, compliance with PAD-34 document. |
11/18/2019 | ZELIN CANCHOLA | COT NON-DSD | TRAFFIC | Completed | No adverse comments. Standard requirements will apply |
11/19/2019 | LOREN MAKUS | ENGINEERING | REVIEW | Completed | 1. Requires updated DP for entire site. 2. Must be consistent with master drainage report. |
11/20/2019 | ELISA HAMBLIN | ZONING | REVIEW | Completed | CDRC Thursday Pre-Submittal Transmittal PDSD Zoning Review FROM: Elisa Hamblin, AICP; Principal Planner PROJECT: Thursday Pre-submittal meeting - T19PRE0211 Address: 3950 E Irvington Rd Parcel(s): 140-02-002C Zoning: PAD-34 Existing Use: Utility - Generating System Proposed Use: Utility - Generating System TRANSMITTAL DATE: November 20, 2019 COMMENTS: 1. Development must comply with the Administrative Manual Section 2-06 - Development Package. 2. The proposal is the for the addition of a fueling station for use by TEP only (not public access). The use is permitted per PAD-34. 3. Parking at a ratio of 1 space per employee is required. Updated information should be submitted with development package to verify this standard is met. 4. Ensure compliance with the development standards of PAD-34 and the Procedures for Development Review as found in Section IV.B. of the PAD document. 5. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards. If you have any questions please contact me at elisa.hamblin@tucsonaz.gov or (520) 837-4966. |
11/20/2019 | SBEASLE1 | TUCSON WATER NEW AREA DEVELOPMENT | REVIEW | Completed | 230 pm - T19PRE0211 - 3950 E IRVINGTON RD - SITE TEP fueling facility No comments |
11/22/2019 | MASHFOR1 | COT NON-DSD | FIRE | Completed | All TFD requirments will need to be verified at Presubmittal meeting with Glenn D' Auria. |