Plan Number: T19PRE0022
Parcel: Unknown

Review Status: Completed

Review Details: PREAPPLICATION

Plan Number - T19PRE0022
Review Name: PREAPPLICATION
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
02/12/2019 ANDREW CONNOR LANDSCAPE REVIEW Completed Show compliance with landscaping and screening requirements by locations, material descriptions, and dimensions. Specific plant or hardscape material shall be detailed on a landscape plan. A detailed landscape plan is required. In accordance with Section 2-10.0.0, Landscape Plan Requirements.
7.7. NATIVE PLANT PRESERVATION
7.7.3. APPLICABILITY
The provisions of this section apply to all development as listed below.
A. New Development
All new development proposed in the City of Tucson shall comply with the standards of this section.
02/13/2019 MASHFOR1 COT NON-DSD FIRE Completed Fire Sprinklers (903.2.1.3 A-3) and Fire Alarm (907.2.1 Group A.) will be required in an A-3 occupancy..Condition 2. The fire area has an occupant load of 300 or more.
02/13/2019 LOREN MAKUS ENGINEERING REVIEW Completed East 36th Street is an arterial and Fairland Stravenue is a collector. The future width of 36th Street is 100 feet. The site is within the range of the intersection taper for the intersection of 36th Street and Country Club Road. The future width of Fairland is 76 feet. Clearly show the existing and future right-of-way.
The site is approximately 4.5 acres. Five-year threshold retention is required. The site is not within a balanced or critical basin. Detention is required if development would cause an adverse impact to adjacent properties. Retention areas must be at the downstream parts of the property.
Water harvesting must be maximized.
Six-foot sidewalks are required along Fairland Stravenue since there is curb along this frontage.
The existing sidewalk along 36th Street must be replaced if less than 4 feet wide or in poor condition.
02/14/2019 ZELIN CANCHOLA COT NON-DSD TRAFFIC Completed No Adverse comments from TDOT. Standard requirements will apply.

No curb and sidewalk will be required along Bantly.
02/14/2019 ELISA HAMBLIN ZONING REVIEW Completed CDRC Thursday Pre-Submittal Transmittal
PDSD Zoning Review

FROM: Elisa Hamblin, AICP; Principal Planner

PROJECT: Thursday Pre-submittal meeting (T19PRE0022)
Address: 3000 E Fairland Stravenue
Parcel(s): 13005686A
Zoning: C-1
Existing Use: Vacant
Proposed Use: Civic - Religious Use

TRANSMITTAL DATE: February 14, 2019

COMMENTS:
1. Development must comply with the Administrative Manual Section 2-06 - Development Package.
2. The proposed use of the site is religious with multi-family housing. Both uses are permitted in the C-1 zone. Religious use is subject to use-specific standard 4.9.13.O.
3. The maximum building height in a C-1 zone is 25' for residential and 30' for nonresidential uses.
4. Fairland Sv and 36th St are designated at Major Streets & Routes. The setback on all three street frontages is 21' or the height of the structure (whichever is greater) as measured from the back of future curb. The interior property line setback is 0 ft, with the exception of the proposed housing, which would require a 10' or ¾ height setback to the interior property line.
5. Vehicle parking for Religious Use is required at 1 space per 100 sq. ft. GFA in all combined public assembly areas or areas where religious services are held, whichever is applicable. For multiple or mixed use development where Religious Use is the principal land use, the total number of motor vehicle spaces required is the number required for the Religious Use or the sum of those required for other uses on the site, whichever is greater. In the current configuration, the total number of required parking is approximately 97 spaces. The current draft proposal includes 200 spaces.
6. Both short-term and long-term bicycle parking will need to be provided on site.
7. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards.

If you have any questions please contact me at elisa.hamblin@tucsonaz.gov or (520) 837-4966.
03/05/2019 AHINES2 TUCSON WATER NEW AREA DEVELOPMENT REVIEW Completed Comments for T19PRE0022 - 3000 E Fairland SV

1) Tucson Water requires an applicant to follow processes outlined on our website. Please see the following link.

https://www.tucsonaz.gov/water/contractors-developers-and-engineers

2) A water availability letter is the first step. Please fill out the form found at the above link and email to Kellie Anderson (contact info found on form)

3) A water master plan is required. Please see checklist and submit for review. Looping of the water lines is required. Fire flow must be determined and approved by the fire department prior to submittal.

4) After approval of the water master plan a design water plan is required. Please see checklist and submit for review. Must comply with redlines to be provided as part of master plan approval.

Payment and plans submittal can be done on line at the web link provided above.

Thanks.

Paul Baughman, PE, CFM
Civil Engineer
Tucson Water
310 W Alameda St.
Tucson, AZ 85701
520-837-2048