Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Plan Number: T19PI00023
Parcel: Unknown

Address: Unknown

Review Status: Completed

Review Details: PIA - SUBMITTAL

Plan Number - T19PI00023
Review Name: PIA - SUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
12/02/2020 GARY WITTWER DOT LANDSCAPE REVIEW Approved
12/02/2020 RLEIGH1 UTILITY CLEARANCES COT STREETS DIVISION Completed Please submit Utility Notification receipt from TEP and COX Communications
12/02/2020 ZELIN CANCHOLA DOT TRAFFIC REVIEW Reqs Change 1- Sheet 10, Existing sign near Sta 64+25: what is this existing sign called out for removal? Does it need to be relocated at a similar location off the new roadside edge?

2- Sheet 10, TWLTL: it appears that the obliteration of the TWLTL for site egress is roughly from Sta 217+50 to Sta 218+00, but it may be helpful for the contractor to have the beginning and end stations for the obliteration called out on this sheet.

3- Sheet 19, OST: at the western end of the new striping, it may be helpful for the contractor if the starting locations for the YDS4 and WS6 stripes are called out. Please call out the MCR stations at both ends of the new driveway near Sta 57+75, as well. In general, more station starting and stopping points where stripes begin/change type/end would be beneficial.

4- Sheet 20, both roads: the same comment about station callouts for striping applies here, too.

Greg Orsini, P.E.
Department of Transportation & Mobility
City of Tucson
(C) 520-268-5036
Gregory.Orsini@tucsonaz.gov
12/02/2020 RICHARD LEIGH PIA COORDINATOR CUSTOMER CALLED; PLANS @ AMBASSSADOR Completed
12/02/2020 JIM FEMLING DOT STREET MAINTENANCE REVIEW Approved
12/02/2020 ERNIE ENCINAS DOT_ELEC REVIEW Approved
12/02/2020 RICHARD LEIGH DOT ENGINEERING REVIEW Reqs Change December 1, 2020

SUBJECT: Offsite Improvement Plans for Northwest Medical Center - Houghton

PROJECT REVIEWER: Richard Leigh, DTM Eng. Review

RESUBMITTAL REQUIRED: TDOT Permit Review Section has reviewed the subject PIA paving plan and does not recommend approval at this time. The following comments need to be addressed and plans revised prior to resubmittal. Please include a response letter addressing the following comments.


1. Sheet 2: Revise construction Grading Note 35 to indicate that the asphaltic concrete shall conform to PAG's Replacement Specification for Section 406 Asphaltic Concrete, dated December 12, 2019.

2. Sheet 1 through 20: Use current DTM title blocks. See Engineering Plan Template at: https://www.tucsonaz.gov/files/transportation/Engineering_Plan_Templates_Dec_2019.pdf

3. Sheet 7, Detail M1: Provide a pedestrian opening in the channelizing island.

4. Place a note on the plan indicating that Old Spanish Trail is under a pavement cut moratorium until June 10, 2021. A mill and inlay will be required for the entire width of the impacted lane.

5. Revise plan set to use only one stationing system.

6. Revise roadway profiles to include a profile of the existing and proposed edge of pavement along Old Spanish trail and Houghton Rd. Include existing grade, label all grade brakes with stationing and grades and indicate running slopes.

7. Clearly indicate proposed slope protection and grading details for all new established slopes.

8. Provide complete grading details for reconfigured grater ditches.

9. Please Refer to redline drawings for additional comments and comment details.

If you have any questions, I can be reached at 520-237-8692 or emailed at Richard.Leigh@tucsonaz.gov.
12/02/2020 RICHARD LEIGH PIA COORDINATOR OUT TO CUSTOMER Completed
12/02/2020 RLEIGH1 UTILITY CLEARANCES COT WATER NEW DEVELOPMENT Completed Please submit Utility Notification receipt from TEP and COX Communications
12/02/2020 RLEIGH1 UTILITY CLEARANCES PC WASTEWATER MGMT Completed Please submit Utility Notification receipt from TEP and COX Communications
12/02/2020 RLEIGH1 UTILITY CLEARANCES QUEST COMMUNICATION Completed Please submit Utility Notification receipt from TEP and COX Communications
12/02/2020 RLEIGH1 UTILITY CLEARANCES TUCSON ELECTRIC POWER CO Needs Review Please submit Utility Notification receipt from TEP and COX Communications
12/02/2020 RLEIGH1 UTILITY CLEARANCES COX COMMUNICATION Needs Review Please submit Utility Notification receipt from TEP and COX Communications
12/02/2020 RLEIGH1 UTILITY CLEARANCES SOUTHWEST GAS CORP Completed Please submit Utility Notification receipt from TEP and COX Communications
12/02/2020 RLEIGH1 UTILITY CLEARANCES EL PASO NATURAL GAS Completed Please submit Utility Notification receipt from TEP and COX Communications
12/02/2020 RLEIGH1 UTILITY CLEARANCES KINDER MORGAN ENERGY Completed Please submit Utility Notification receipt from TEP and COX Communications