Plan Number: T19PI00019
Parcel: Unknown

Address: Unknown

Review Status: Completed

Review Details: PIA - SUBMITTAL

Plan Number - T19PI00019
Review Name: PIA - SUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/11/2019 ZELIN CANCHOLA DOT TRAFFIC REVIEW Reqs Change October 11, 2019
Offsite Improvement Plan127 S 5th Avenue
Reviewer Zelin Canchola

Existing striping in front of new vertical curb bumpout requires obliteration and new striping will need a minimum width of 11 feet.

Place note or show new striping (include transition from existing)
10/11/2019 RICHARD LEIGH PIA COORDINATOR CUSTOMER CALLED; PLANS @ AMBASSSADOR Completed
10/11/2019 RICHARD LEIGH DOT ENGINEERING REVIEW Reqs Change October 5, 2019

SUBJECT: 127 South 5th Avenue Offsite Improvements

PROJECT REVIEWER: Richard Leigh, TDOT, TDOT Eng. Review

RESUBMITTAL REQUIRED: TDOT Permit Review Section has reviewed the subject PIA paving plan and does not recommend approval at this time. The following comments need to be addressed and plans revised prior to resubmittal. Please include a response letter addressing the following comments and return redlined drawings with subsequent submittal.
1. Add the plan number "I-2019-036" in the title block of each sheet.

2. Add PIA activity number "T19PI0019" on cover sheet.

3. Add Development Plan Number on cover sheet.

4. Revise drawing to depict and label all existing utility poles, parking meters, building downspouts, trees, tree stumps, signs and etc. Also indicate their disposition.

5. Sheet 1: Revise General Construction Note #3 to indicate the use of City of Tucson Mix #2.

6. Sheet 1: Revise drawing legend to include all lines and symbols used in drawing.

7. Sheet 2: Indicate engineer's pavement subgrade preparation recommendations for the pavement replacement on Herbert Ave.

8. Sheet 2: Revise drawing to include all proposed improvements in the ROW. Provide complete details for new curb, sidewalk, downspouts and driveway aprons.

9. Provide details for the proposed sidewalk brick pavers (concrete brick are preferred) along 5th Ave. and Herbert Ave. Provide paver pattern detail.

10. Sheet 2: Include existing and proposed gutter and top of curb profile in Herbert Avenue profile view.

11. Sheet 2: Provide stationing, offsets and elevations for proposed curb islands on 5th Avenue.

12. Sheet 2: Provide radius returns on proposed curb islands on 5th Avenue.

13. Sheet 2: Indicate the final surface treatment for the proposed curb islands on 5th Avenue.

14. Provide details for any signing and striping changes. It appears that the center line striping on 5th Ave will have to be revised to accommodate proposed islands.

15. Sheet 2: Revise drawing to square off pavement replacement area on 5th Street, see redlines.

16. Sheet 2: Call out and provide details of the proposed vertical transitions for curb and sidewalk on 5th Ave, include stationing, offsets, grades and elevations.

17. Submit a PDF copy of the approved development plan with next submittal.

18. Please Refer to redline drawings for additional comments and comment details.

If you have any questions, I can be reached at 837-6647 or emailed at Richard.Leigh@tucsonaz.gov.
10/17/2019 RICHARD LEIGH PIA COORDINATOR OUT TO CUSTOMER Completed
10/17/2019 GARY WITTWER DOT LANDSCAPE REVIEW Approved
10/17/2019 RLEIGH1 UTILITY CLEARANCES COT STREETS DIVISION Completed
10/17/2019 RLEIGH1 UTILITY CLEARANCES COT WATER NEW DEVELOPMENT Completed
10/17/2019 RLEIGH1 UTILITY CLEARANCES PC WASTEWATER MGMT Completed
10/17/2019 RLEIGH1 UTILITY CLEARANCES QUEST COMMUNICATION Completed
10/17/2019 RLEIGH1 UTILITY CLEARANCES TUCSON ELECTRIC POWER CO Completed
10/17/2019 RLEIGH1 UTILITY CLEARANCES COX COMMUNICATION Completed
10/17/2019 RLEIGH1 UTILITY CLEARANCES SOUTHWEST GAS CORP Completed
10/17/2019 RLEIGH1 UTILITY CLEARANCES EL PASO NATURAL GAS Completed
10/17/2019 RLEIGH1 UTILITY CLEARANCES KINDER MORGAN ENERGY Completed