Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T19CM09261
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/19/2020 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | FROM: David Rivera PDSD Zoning Review Section PROJECT: T19CM09261 Shell Building (2nd Review) 2121 N Craycroft Rd TRANSMITTAL DATE: February 19, 2020 DUE DATE: February 27, 2020 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 01. COMMENT: Zoning has reviewed the plans for compliance with the last revised and approved Development Package (DP) for the subject property, DP17-0182. The review is also subject to rezoning C9-16-16. 02. COMMENT: Site plan shown does not match revised and approved DP17-082 specifically in regard to the sidewalk extension to the east property line along the south side of the building 7. Revise the site plan on sheet 3 to depict the sidewalk extending to the east property line of Lot 7. 03. COMMENT: Change note 2.B. under Code Study - 2018 International Building Code to correctly state the height requirements for this project, which is a max of 20'as approved for buildings 4-8 per rezoning condition 7. The max height of the building should be listed as 20 feet or as measured to the midpoint of the tallest roof. (Keep in mind that condition 7 restricts the height of Building 7 to 20 feet.) If you have any questions about this transmittal, Contact David Rivera at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields at (520) 837-4956 or email Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Corrected Building Plans as requested |
| 03/02/2020 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Completed | |
| 03/02/2020 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Comment not addressed. [Initial comment: Revise the connection of the building drain to the private sewer collection system as shown on sheet ASP.1; the private sewer collection system flows from west to east. Reference: Section 706.3, IPC 2018.] |
| 03/03/2020 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Reqs Change | refer to zoning comments. once the site plan matches the approve Development Package Engineering can approve |