Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T19CM08914
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/13/2020 | TOM WEIDEMAN | BUILDING-COMMERCIAL | REVIEW | Approved | PER RMACCOY |
| 01/13/2020 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 01/13/2020 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Provide a design for the mounting shelf for the water heater along with structural calculations to show that the water heater is safely supported from the building structure. Reference: Section 301.2, IPC 2018. 2. The water heater detail on sheet P-1 shows both a shut off valve and a check valve downstream of the vacuum relief valve and the thermal expansion tank. Install the proposed vacuum relief valve and shut off valve for the water heater per the manufacturer's listing information, i.e. with no valves located between the vacuum relief valve, the thermal expansion tank, and the water heater. Reference: Section 303.2, IPC 2018. 6. Provide the listing information for the specified thermostatic mixing valve for the lavatories. Reference: Sections 303.4, 419.5, and 607.1.2, IPC 2018. 7. Provide the gas load for each of the existing unit heaters. Reference: Sections 402.1 and 402.3, IFGC 2018. |
| 01/13/2020 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 01/13/2020 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. The one-line diagram shows panel 'LD' with a 50amp MCB. The panel schedule shows 125amp MLO. Please clarify. 2. Revise the 2012 IECC com check to the current 2018. Ref; 2018 IBC 107.2.1, 2017 NEC, City of Tucson Commercial Plan Submittal requirements. |
| 01/13/2020 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Condensate drains may not terminate over a roof drain or gutter unless the roof drain or gutter terminates at or below grade in an area capable of absorbing the condensate flow without surface drainage. Reference: Section 307.2.1, IMC 2018, as amended by the City of Tucson. 2. Provide heating and cooling load calculations to justify the total heating/cooling capacities of the five existing and two new HVAC units serving the building. Reference: Section C403.1.1 and C403.3.1, IECC 2018. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 01/24/2020 | SBORZAK1 | REJECT SHELF | Completed |