Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T19CM08500
Review Name: COMMERCIAL - NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 11/27/2019 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | FROM: David Rivera PDSD Zoning Review Section PROJECT: T19CM08500 - New Building (Office / Workshop - Commercial Use Group) Building Plan Review (1st Review) Sunland Asphalt / Related to DP19-0295 2630 E. Ginter Road / I-1 Zoning TRANSMITTAL DATE: November 27, 2019 DUE DATE: December 17, 2019 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. COMMENT: Zoning has done a cursory review of the building plans. (Prior to any approval of the building plans an approved DP will be required.) As of this building review by zoning, a DP for this location has not been submitted for review. Zoning cannot verify that the building plans are in compliance with the DP (Eventual Approved DP) at this time and will review the building plans on the next submittal. Zoning will review the building plans for consistency with the DP as it relates to the zoning review purview of the Building footprint, Height, square footage, site conditions etc. Be aware that zoning cannot approve the building plans until the DP is approved by review staff and that PDSD Commercial Plans reviewers have approved the building plans. If you have any questions about this transmittal, Contact David Rivera on Tuesday, Wednesday or Thursday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov |
| 11/29/2019 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Approved | |
| 12/03/2019 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 12/05/2019 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 12/10/2019 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 12/18/2019 | LOREN MAKUS | ENGINEERING | REVIEW | Reqs Change | DP19-0295 must be approved first. |
| 12/18/2019 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Completed | |
| 12/18/2019 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Horizontal branches shall connect no closer than ten diameters downstream of the bases of vertical stacks. Reference: Section 704.3, IPC 2018. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 01/13/2020 | KROBLES1 | OUT TO CUSTOMER | Completed |