Permit Review Detail
Review Status: Completed
Review Details: 3RD PARTY REVIEW - COMMERCIAL
Permit Number - T19CM08164
Review Name: 3RD PARTY REVIEW - COMMERCIAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 11/12/2019 | MROSS2 | FIRE | REVIEW | Approved | |
| 11/20/2019 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | FROM: David Rivera PDSD Zoning Review Section PROJECT: T19CM001864 - New Building (Commercial Use Group - Administrative Office) Building Plan Review (1st Review) Sever Franks / Related to DP19-0274 3742 W. River Road / O-3 Zoning TRANSMITTAL DATE: November 20, 2019 DUE DATE: December 6, 2019 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. COMMENT: Zoning has reviewed the building plans for compliance with the current unapproved development package. While the building plans are consistent with the unapprovedDP as it relates to the zoning review purview of the Building footprint, Height, square footage, site conditions etc., zoning cannot approve the building plans until the 3rd Party and PDSD Commercial Plans reviewers have approved the building plans and the DP is approved. 2. COMMENT: Zoning will review the building plans on the next submittal as it relates to the zoning review purview and compare the building plan footprint, building height, and square footage and location to ensure continued consistency with the DP. 3. COMMENT: Once the plans have been reviewed and approved by PDSD Commercial Plan Reviewers and zoning has verified consistency with the approved and signed DP, the building plans can be approved by zoning. 4. COMMENT: On the site plan sheet A1.0, a carport structure is proposed but no drawings were included in the package. If the parking canopy structure is to be permitted under separate permit add a note next to the carport drawing on sheet A1.0 stating that the carport application for construction will permitted under separate permit. If you have any questions about this transmittal, Contact David Rivera on Tuesday, Wednesday or Thursday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov |
| 12/05/2019 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 12/09/2019 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Reqs Change | T19CM08164 1) Once the development package has been approved and all outstanding commercial review comments have been completed engineering can approve the building plans |
| 12/17/2019 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Needs Review | |
| 12/17/2019 | STANTEC | 3RD PARTY REVIEW-COMMERCIAL | AT 3RD PARTY OFFICE | Completed | |
| 12/17/2019 | AMARTIN1 | ZONING HC | REVIEW | Needs Review | |
| 12/17/2019 | AMARTIN1 | ADA | REVIEW | Needs Review |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 12/17/2019 | PMARTIN1 | OUT TO CUSTOMER | Completed |