Permit Number: T19CM07854
Parcel: 137055300

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T19CM07854
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/29/2019 MROSS2 FIRE REVIEW Reqs Change -Change note on page A-0 to note that building is fully sprinklered
-Provide specifications, quatities and location of med gas
11/01/2019 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Sheet A-O , Project Information , OFFICE AREA - the occupant load factor is incorrect , amend the number of occupants using the correct occupant load factor . IBC Table 1004.5 .
2. Amend exit widths with the correct occupant load . IBC107.2.1.
3. Provide the minimum number of required plumbing fixtures per IBC chapter 29 .IBC Table 2902.1.
4. Provide the expiration date on the registrants seal . IBC 107.2.1.
5. Provide exit access travel distances on plan sheet A-0.1. IBC 1017.
6. Provide Structural Calculations for roof installation of new mechanical unit . IBC 107.2.1.
11/18/2019 ROBERT SHERRY WATER REVIEW Reqs Change Verify the size of the water meter serving this suite, the size of the backflow preventer associated with the water meter, and the total water demand served by the water meter. Reference: Section 107.2.1, IBC 2018
11/18/2019 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Provide the minimum plumbing facilities required by Table 2902.1 and Section 2902.2, IBC 2018, for business occupancy (e.g. drinking fountains and service sink).
2. Clarify how the specified water closet carriers will fit the 3-5/8" stud walls. Reference: Sections 303.2 and 405.4.3, IPC 2018.
3. The developed length of the hot water supply piping appears to be greater than fifty feet; provide a method for maintaining the temperature of the hot water supply system. Reference: Section 607.2, IPC 2018 and C404.5, IECC 2018.
4. Verify that the distance from the hot water source to the hot water termination for the public lavatories complies with the requirements of Section C404.5, IECC 2018.
11/18/2019 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Provide heating and cooling load calculations to justify the heating/cooling capacities of the specified HVAC unit, HP-4. Reference: Section C403.1.1 and C403.3.1, IECC 2018.
2. Show that each rooftop unit has a thermostatic control that provides for off-hour and set-back control, automatic shutdown and automatic start-up control (i.e. the thermostat is capable of automatically adjusting the start time of the HVAC equipment in order to bring the interior conditions to the desired temperature at the start of occupancy) and, if the thermostat does not require manual changeover from the heating and cooling modes, it restricts set point overlap. (Note that there is no Section C403.2.4 in the 2018 IECC.) Reference: Section C403.4.2 through C403.4.2.3, IECC 2018.
3. Provide information on the sequence of operation for the restroom exhaust fans to show that all of the air supplied to the restrooms will be exhausted. Reference: Section 403.2.1 (4), IMC 2018.
4. Clarify that keynote 1 on sheet M1.1 also applies to HP-4 with respect to the required flow rate of outside air. Reference: Section 403.3, IMC 2018.
5. How is ventilation being provided to the corridors? Reference: Sections 401.2 and 401.3, IMC 2018.
6. Provide a return grille for OP-17 to avoid using the corridor as a return air duct. Reference: Section 601.2, IMC 2018.
11/21/2019 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Approved