Permit Number: T19CM07773
Parcel: 12605009B

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T19CM07773
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/22/2020 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change The extent of the design to be deferred shall be shown on the construction documents and approved by the building official prior to completion of the current review. Reference: Section 107.3.4.1, IBC 2018. [Second comment: Show how the grease exhaust is going to be revised to meet the code requirements (i.e. not just notes). The current exhaust fan appears to be located partly under the roof on the west side of the truck, definitely not 40" above the roof of the truck and the fan also appears to be a down blast fan.] [Initial comment: Verify that the installation of the grease exhaust fan complies with Sections 506.3.13.1, 506.3.13.3, 506.5.3, 506.5.4 and 506.5.6, IMC 2018.]
10/01/2020 STEVE SHIELDS ZONING REVIEW Reqs Change PDSD TRANSMITTAL

FROM: Steve Shields
Section Manager

PROJECT: T19CM07773 - Babylon Market
Building Plan Review (2nd Review) / Relate to DP18-0207
3954 E Speedway / C-2 Zoning

TRANSMITTAL DATE: October 1, 2020

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

1. COMMENT: Zoning will review the building plans on the next submittal as it relates to the zoning review purview and compare the building plan footprint, building height, and square footage and location to ensure consistency with DP18-0207, once it has been approved.

2. COMMENT: Once the plans have been reviewed and approved by PDSD Commercial Plan Reviewers and zoning has verified consistency with the DP, the building plans can be approved by zoning.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956
10/07/2020 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Per previous comments, provide the structural calculations for the steel awning. Your responses indicate those calculations are included in the submittal set, but they are not there.
10/20/2020 SBLOOD1 ENGINEERING REVIEW Reqs Change Approval of the Development Package (DP18-0207) is required prior to approval of the building plans. Once the DP is approved the building plans will be reviewed

Stephen Blood