Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T19CM07773
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/08/2020 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 04/08/2020 | LOREN MAKUS | ENGINEERING | REVIEW | Reqs Change | DP must be approved first. |
| 04/09/2020 | DJELLEN1 | ZONING | REVIEW | Reqs Change | FROM: David Jellen PDSD Zoning Review Section PROJECT: T19CM07773 – Babylon Market Building Plan Review (1st Review) / Relate to DP18-0207 3954 E Speedway / C-2 Zoning TRANSMITTAL DATE: April 9, 2020 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. COMMENT: Zoning will review the building plans on the next submittal as it relates to the zoning review purview and compare the building plan footprint, building height, and square footage and location to ensure consistency with DP18-0207, once it has been approved. 2. COMMENT: Once the plans have been reviewed and approved by PDSD Commercial Plan Reviewers and zoning has verified consistency with the DP, the building plans can be approved by zoning. 3. COMMENT: Ensure that the conditions included with the approved IPP, Board of Adjustment, and DDO are included as notes on the plan. If you have any questions about this transmittal, contact David Jellen at (520) 837-4082 or by email at David.Jellen@tucsonaz.gov. |
| 04/09/2020 | MARTIN BROWN | FIRE | REVIEW | Reqs Change | I believe that, now that the food truck is part of the building, the hood above the fryer needs a type 1 hood, which by definition requires a kitchen exhaust hood fire prevention system. Confirm with Bob Sherry of PDSD. |
| 04/09/2020 | DJELLEN1 | ZONING | REVIEW | Reqs Change | FROM: David Jellen PDSD Zoning Review Section PROJECT: T19CM07773 – Babylon Market Building Plan Review (1st Review) / Relate to DP18-0207 3954 E Speedway / C-2 Zoning TRANSMITTAL DATE: April 9, 2020 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. COMMENT: Zoning will review the building plans on the next submittal as it relates to the zoning review purview and compare the building plan footprint, building height, and square footage and location to ensure consistency with DP18-0207, once it has been approved. 2. COMMENT: Once the plans have been reviewed and approved by PDSD Commercial Plan Reviewers and zoning has verified consistency with the DP, the building plans can be approved by zoning. 3. COMMENT: Ensure that the conditions included with the approved IPP, Board of Adjustment, and DDO are included as notes on the plan. If you have any questions about this transmittal, contact David Jellen at (520) 837-4082 or by email at David.Jellen@tucsonaz.gov. |
| 04/14/2020 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Appeal to the building official required for the walk-in coolers and freezers 2. The Type 1 hood in the trailer exhausts 4,000 CFM and the make-up air unit supplies 3,500 CFM. Where is the remaining make up air coming from? Verify that the installation of the grease exhaust fan complies with Sections 506.3.13.1, 506.3.13.3, 506.5.3, 506.5.4 and 506.5.6, IMC 2018 |
| 04/14/2020 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Verify that the HEalth Dept is satisfied with the lack of a hand sink near the new 3-compartment sink. 2. Correlate the new fixture tags (e.g. P-1, P-2 & P-3) with the scheduled fixture descriptions. 3. Verify that the water heater located in the trailer has a thermal expansion tank. 4. Revise the notes in the main building to point at the correct fixtures (e.g. the note for the hand sink is pointing to the 3-compartment sink, etc.) |
| 04/15/2020 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet T1.0: Please provide a Code Analysis for the addition of the mobile unit. Indicate SF, Construction Type, Occupancy Classification, Occupant Load, and a Narrative for the use of the mobile unit. 2. Sheet T1.0: Please provide an analysis of the Allowable Area, Exiting Requirements, Travel Distance, and Plumbing Fixtures Required. 3. Sheet A1.0; Dimensioned Floor Plan: An unfinished section is cut through the existing steel awning and the mobile unit. Please revise. Where is this section cut on the plan? 4. Sheets A1.0 and S1.0: Please add north arrows to the plans. 5. Sheet S1.0; Framing Plan: Please provide structural calculations for the steel awning as required. What is the reason for adding an additional steel stud joist to each existing joist? 6. General: Please provide written responses to all review comments. |
| 04/15/2020 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
| 12/31/2019 | ROBERT SHERRY | WATER | REVIEW | Completed |