Permit Number: T19CM07097
Parcel: 124150330

Address:
941 E 19TH ST

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T19CM07097
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/06/2020 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Comment not addressed by the revised structural letter. [Initial comment: Provide structural calculations and details to show that the Type I hoods are supported from the building structure in accordance with Section 507.2.4, IMC 2018 (the hood hanging weight plus the weight of personnel working in or on the hood). Reference: Section 302.1, IMC 2018.]
2. Comment not addressed. [Initial comment: Verify the make-up air scheduled for hoods KH-1A and KH-2A; the manufacturer listing information shows a lower total supply airflow rate for these hoods. Reference: Section 304.1, IMC 2018.]
3. Comment not addressed. [Initial comment: Verify that the exhaust and make-up airflow rates for the building are approximately equal. Reference: Sections 501.4 and 508.1, IMC 2018.]
4. Comment not addressed. [Initial comment: Demonstrate energy code compliance for the addition to the building envelope using calculations based on the current code. Reference: Sections C103.2, C303, and C502.1, International Energy Conservation Code 2018.]
5. Provide the walk-in cooler and freezer meet the performance standards of Tables C403.10.2.1 (2) and C403.10.2.1 (3), IECC 2018. [Initial comment: Provide specifications for the walk-in coolers and walk-in freezers; Show that these units comply with Section C403.10.4, IECC 2018.]
05/08/2020 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Comment not resolved. Provide the specifications for the lavatories (P-1 and P1A). Include the lavatory and faucet specifications on the drawings. Provide the specifications for the lavatories (P-1 and P1A). [Initial comment: Provide the specifications for the lavatories (P-1 and P1A) and the associated faucets; specifications were not found in the architectural drawings. Metering faucets are required. Reference: Section 107.2.1, IBC 2018 and Section 419.6, IPC 2018, as amended by the City of Tucson.]
2. Comment not resolved; the appeal has not yet been approved or denied. [Initial comment: For public toilet facilities, the required lavatory shall be located in the same room as the water closet. Reference: Section 405.3.2, IPC 2018.]
3. The faucet literature states that a 10-second time out is an option. If this time out is not adjustable, note that the water flow must continue for at least 10-seconds for accessibility; 9-seconds is not compliant. [Initial comment: Verify that the specified sensor faucet for the public lavatories has an automatic time-out so that it will dispense a maximum of 0.25 gallons per metering cycle. Reference: Section 419.6, IPC 2018, as amended by the City of Tucson and Section 606.4, ICC/ANSI A117.1-09.]
4. Appliances (e.g. beverage dispensers, ice makers, etc.) to be directly connected to the water supply system that do not have listed, integral backflow preventers or integral air gaps conforming to Section 608.14.1, IPC 2018 require backflow prevention. Specify the type of backflow prevention device required for each water connection. Reference: Sections 608.1 and 608.3, IPC 2018.
6. Comment not addressed. [Initial comment: If the discharge temperature of the dishwasher or rack washer will be greater than 140 degrees Fahrenheit, show that the temperature rating of the drainage pipe material is suitable for the highest temperature of the wastewater. Reference: Section 702.5, IPC 2018.]
7. Comment not addressed. [Initial comment: Provide gas service to the fireplace located at the east end of the patio (see sheet a3.0 and detail 8/a9.3). Reference: Section 107.2.1, IBC 2018.]
05/18/2020 STEVE SHIELDS ZONING REVIEW Reqs Change FROM: Steve Shields
Site Section Manager

PROJECT: T19CM07097 (Related to DP16-0196)
TI and Building Addition (2nd Review)
941 E. 19th Street / I-1 Zoning

TRANSMITTAL DATE: May 18, 2020

DUE DATE: May 21, 2020

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

As not plans were resubmitted and no comment response letter provided the following previous comments still apply.

01. COMMENT: Zoning has done a review of the building plans. In addition, while the building are consistent as it relates to the zoning review purview (as noted above) zoning cannot approve the building plans until the Commercial Plans reviewer(s) have approved the building plans

02. COMMENT: Zoning will review the building plans on the next submittal to assure consistency with the approved DP. If any changes are necessary to the building plans due to plan review comments that affect zoning requirements the DP will have to be revised to reflect the changes. Once the Commercial Plans reviewers approve the building plans zoning can approve the plans.

03. COMMENT: COMMENT: Clearly define the office area square footage. It appears that the office area approved on the DP is a lot smaller than what is depicted on the building plans. The DP may have to be revised prior to the approval of the building plans. The proposal depicted on the building plans as it relates to the restaurant and office areas of the existing building do not match the approved DP

04. COMMENT: COMMENT: Add the height of the proposed building on the elevation sheet.

If you have any questions about this transmittal, contact Steve Shields any time during the week at (520) 837-4956 or email Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Corrected Building Plans
06/08/2020 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. General: No new drawings have been submitted. Previous Building comments were not resolved. See previous review for all comments.