Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T19CM06562
Parcel: 13314227C

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T19CM06562
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/22/2019 MARTIN BROWN FIRE REVIEW Approved
10/23/2019 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please address the following electrical plan review comments. Also provide a written response.
1. Provide full compliance with the 2018 IECC for the lighting.
2. Provide a reference note on the plans to provide compliance with NEC article 517.13 for wiring methods (where applicable).
3. Provide electrical plans sealed by an Electrical Engineer registered in the State of Arizona as required per the State of Arizona Revised Statutes and The City of Tucson Commercial Plan Submittal Requirements. www.tucsonaz.gov/pdsd.
Ref; 2018 IBC sec 107.2.1, 2017 NEC. City of Tucson Commercial Plan Submittal requirements.
10/24/2019 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. All Sheets: A large note indicates this is a drawing set issued for permit-not for construction. All drawings submitted for permits must be construction-ready. Please remove that portion of the note.
2. Sheet G-000; Room Schedules: Although this is not a change of use, is the new occupant load greater than the original occupant load for this area due to the additional rooms (per the Project Description). Please verify.
3. Sheet LS-050; Use Group/Occupancy: Per the IBC Section 308.3.1, please indicate on the drawing if this is a Condition 1 or Condition 2.
4. Sheet LS-050; Travel Distance: The Code Review indicates a travel distance not greater than 50' from any point in a sleeping room. Please add to that note the 50' is to the exit access door.
5. Sheet LS-050; General Building Heights/Areas: Please indicate on the drawing the unlimited building area is per the IBC Table 506.2.
6. Sheet LS-050: Please verify on the drawings that the requirements of the IBC Section 1107.5.3 for Accessible units and for Type B units are met.
7. Sheet LS-050: A note for Special Inspections indicates to follow Chapter 17 of the IBC. Please list on this sheet the special inspections required, and submit a Sprcial Inspection Certificate with Parts A and B completed (see tucsonaz.gov/PDSD for that Certificate).
8. Sheets LS-110 and LS-111; Life Safety Plans: Are the common paths of egress travel and the exit access travel distances missing from this sheet? Please verify.
9. Sheet LS-121; Partition P-10: Please add a U.L. Listing Number to this partition.
10. Sheet LS-122; Partitions: Please add a U.L. Listing Number to these partitions.
11. Sheets A-111, A-112, A-113, A-114, A-121, A-121A, A-122, A-122A, A-123, and A-124; Partitions: Note 10 indicates that partitions shall be laterally braced to underside of existing structure as required. Per the IBC Section 1607.15, interior walls/partitions shall have adequate strength to resist a minimum horizontal load of 5 PSF. Please indicate lateral bracing size and spacing in this note. In addition, provide details at the top of the partition and at the existing structure above, indicating the connection of the bracing at those locations.
12. Sheets A-121, A-121A, A-122, A-122A, A-123, and A-124; Floor Plans: Please add a note to these sheets that references Sheets LS-120, LS-121, LS-122, and LS-123 for the Partition Type Schedules.
13. Sheets A-151, A-152, A-153, and A-154; Floor Plans: Please add a note to these sheets that references Sheet A-710 for Finish Schedules.
14. Sheets A-163 and A-164; Floor Plans: Please add a Wall Protection Legend and a reference to Sheet A-611 for Wall Protection and Signage Details.
15. Sheets A-200, A-201, A-203, A-204, A-205, and A-206; General Notes: Please finish the referred sheet numbers for the Casework Details.
16. General: Please provide written responses to all review comments.

Review by Eric Newcomb
Contact at 520-837-4911 or Eric.Newcomb@tucsonaz.gov
10/29/2019 ROBERT SHERRY WATER REVIEW Completed
10/29/2019 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Provide tempered water for the lavatories in restrooms using approved devices conforming to ASSE 1070. Reference: Sections 419.5 and 607.1.2, IPC 2018.
2. Provide metering faucets for the public lavatories, dispensing a maximum of 0.25 gallons per metering cycle. Verify that the faucets will operate for a minimum time of 10-seconds. Reference: Section 419.6, IPC 2018, as amended by the City of Tucson and Section 606.4, ICC/ANSI A117.1-09.
3. If the showers do not have pre-fabricated receptors, provide details to show that the construction of the receptors complies with the requirements of Section 421.5, IPC 2018.
4. Verify that all of the vents rise vertically to at least 6" above the flood rims of the fixtures they protect prior to running horizontally (see details 5/P2.2, 7/P2.2, and 9/P2.2). Reference: Section 905.4, IPC 2018.
5. Verify that all horizontal vents forming branch vents, relief vents, or loop vents are located at least 6" above the flood rim of the highest fixture served. Reference: Section 905.5, IPC 2018.
6. A common vent is limited to serving two traps or trapped fixtures (see detail 3/P2.2). Reference: Section 911.1, IPC 2018.
10/30/2019 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Completed

Final Status

Task End Date Reviewer's Name Type of Review Description
11/05/2019 SBORZAK1 REJECT SHELF Completed