Permit Number: T19CM06207
Parcel: 12419040H

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T19CM06207
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/05/2019 DAVID RIVERA ZONING REVIEW Reqs Change FROM: David Rivera
PDSD Zoning Review Section

PROJECT: T19CM06207 - New Building Commercial Use Group (Retail Shell)
Building Plan Review (1st Review) Cherry Lofts / Related to Dp19-0175
585 S. Cherry Avenue Building #11 / I-1 to C-1 Zoning Per C9-19-11

TRANSMITTAL DATE: September 5, 2019

DUE DATE: October 1, 2019

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.


1. COMMENT: Zoning has reviewed the building plans for compliance with the current unapproved version of the development package. While the building plans are consistent with the current unapproved version of the DP as it relates to the zoning review purview of the building footprint, Height, square footage, site conditions etc., zoning cannot approve the building plans until the rezoning process has been completed, development package is approved by all CDRC plans reviewers and the building plans are approved by all the PDSD Commercial Plans reviewers.

2. COMMENT: Zoning will review the building plans on the next submittal as it relates to the zoning review purview and compare the building plan footprint, building height, and square footage and location to ensure consistency with the DP and any applicable conditions of related to the rezoning process that may apply to the building design or aesthetics.

3. COMMENT: Once the building plans have been reviewed and approved by PDSD Commercial Plan Reviewers and zoning has verified consistency with the DP and compliance with the rezoning conditions, the building plans can be approved by zoning.


If you have any questions about this transmittal, Contact David Rivera on Tuesday, Wednesday or Thursday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov
09/09/2019 MARTIN BROWN FIRE REVIEW Reqs Change
09/20/2019 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed
09/20/2019 ROBERT SHERRY WATER REVIEW Completed
09/23/2019 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Passed
09/24/2019 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Sheet T1; Deferred Submittals: Please add a reference in this note to follow the IBC Section 107.3.4.1 for Deferred Submittals.
2. Sheet A4.1; Floor Plan: Note 1 indicates dimensions are to center or face of stud. Please remove the portion of that note that indicates "to center".
3. Sheet A4.2; Exterior Elevations: The direction reference for each elevation does not match the directional arrow shown on the Floor Plan (Sheet A4.1). Please coordinate.
4. General: Please provide the Special Inspection Certificate with Parts A and B completed.
5. General: Please provide written responses to all review comments.

Review by Eric Newcomb
Contact at 520-837-4911 or Eric.Newcomb@tucsonaz.gov
09/27/2019 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Approved
10/07/2019 JOHN VAN WINKLE ENGINEERING REVIEW Reqs Change 1) Once the Development Package has been approved, engineering will review the building plans for consistency with the development package
2) Ensure that all applicable roof drains scupper underneath pedestrian circulation areas
10/07/2019 JVWINKL1 LANDFILL REVIEW Passed

Final Status

Task End Date Reviewer's Name Type of Review Description
04/20/2020 LBOWERS1 OUT TO CUSTOMER Completed
04/20/2020 LBOWERS1 REJECT SHELF Completed