Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T19CM05779
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/30/2019 | MARTIN BROWN | FIRE | REVIEW | Reqs Change | Travel distance appears to be calculated from the front of the flower rooms instead of the back. |
| 10/07/2019 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet A0.0; Applicable Codes: Please add the 2009 ICC/ANSI A117.1 accessibility code to this list. 2. Sheet A0.2; Site Plan: Please indicate what the circled numbers 40, 41, 42, and 56 represent. 3. Sheet A0.7; Division 4: Please add the vertical grab bar at the water closet per the ICC/ANSI Figure 604.5.1. 4. Sheet A0.8; Egress Floor Plan: Per the IBC Section 1017.3, the exit access travel distance shall be measured from the most remote point of each room along the natural and unobstructed path of horizontal and vertical egress travel to an exit. Please indicate those distances from the Flower 3 and Flower 4 rooms following a vertical/horizontal path, and revise the travel distance as required. 5. Sheet A0.8; Egress Floor Plan: Please add a north arrow to the plan. 6. Sheet A1.1; Floor Plan: Please add a north arrow to the plan. 7. Sheet A1.1; Wall Schedule (Mark 1 and 6): Please reference the wall stud gauge and spacing on these wall to Sheet A6.0. 8. Sheet A1.1; Wall Schedule (Mark 2): Are the insulated wall panels self supporting for vertical and lateral loads? Please provide specifications for this wall/roof system, and verify the requirements of the IBC Section 1607.15 are met. 9. Sheet A1.1; Wall Schedule (Mark 2): Please verify on the drawings the insulated wall/roof panels meet the requirements of the IBC Section 720 for flame spread index and smoke developed index. Please provide specifications for this wall/roof system. 10. Sheet A1.2; Floor Plan Phase 2: In the Flower Rooms 3 and 4, please verify the exit paths meet the width requirements of the IBC Table 1020.2. 11. General: Please provide written responses to all review comments. |
| 10/09/2019 | RMCCOY1 | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Provide Structural Calculations for roof support of the six new HVAC units. IBC107.2.1 |
| 10/09/2019 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 10/09/2019 | RMCCOY1 | WATER | REVIEW | Passed | |
| 10/09/2019 | RMCCOY1 | PLUMBING-COMMERCIAL | REVIEW | Approved | |
| 10/22/2019 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | FROM: David Rivera PDSD Zoning Review Section PROJECT: T19CM05779 - Tenant Improvement (Retail - MMOCL) Building Plan Review (1st Review) Earth's Healing / Related to T19SA00336 3529 E. Golf Links Road / I-1 Zoning TRANSMITTAL DATE: October 22, 2019 DUE DATE: October 24, 2019 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. COMMENT: Zoning has reviewed the building plans for compliance with the requirements for a MMOCL use and location. While the building plans are consistent with the requirements zoning review purview, zoning cannot approve the building plans until all PDSD Commercial Plans reviewers have approved the building plans. 2. COMMENT: List as reference the Special Application case number T19SA00336 next to the title block of all plan sheets. 3. COMMENT: Once the plans have been reviewed and approved by PDSD Commercial Plan Reviewers Zoning can approve the building plans as it relates to the zoning review purview. If you have any questions about this transmittal, Contact David Rivera on Tuesday, Wednesday or Thursday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov |
| 10/28/2019 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 10/31/2019 | AMARTIN1 | REJECT SHELF | Completed |