Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T19CM05078
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
07/29/2019 | MARTIN BROWN | FIRE | REVIEW | Approved | |
07/31/2019 | ROBERT SHERRY | WATER | REVIEW | Reqs Change | 1. The site utility drawing, C 06.03, shows a single water supply to the proposed hospital. Provide two water service pipes to the hospital per Section 609.2, IPC 2018. 2. What is the total water demand for the hospital? Reference: Section 107.2.1, IBC 2018. |
08/06/2019 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Provide water isometrics and waste and vent isometrics. Reference: Section 107.2.1, IBC 2018. 2. Provide automatic faucets for lavatories located in public restrooms (including staff restrooms). Verify that the automatic faucets will operate for a minimum time of 10-seconds but have an automatic time out to limit the amount of water dispensed to 0.25 gallons per cycle. Reference: Section 419.6, IPC 2018, as amended by the City of Tucson and Section 606.4, ICC/ANSI A117.1-09. 3. Verify that the distance from the hot water source to the hot water termination for the public lavatories (including staff restrooms) complies with the requirements of Section C404.5, IECC 2018. 4. Verify that the pipe size called out for the flush valve for WC-4 will not result in a water velocity greater than that recommended by the pipe manufacturer (e.g. limit the water velocity to less than 8 FPS for copper, PEX, or CPVC piping). At a minimum design flow rate of 25 GPM for a siphonic, flush-valve water closet, a 1" Type L copper pipe has a flow velocity of 9.7 FPS. Reference: Table 604.3, IPC 2018. 5. Revise the plumbing fixture schedule to include hot water for the clinical sink (CS-1). Reference: Section 607.1, IPC 2018. 6. Appliances (e.g. ice makers) to be directly connected to the water supply system that do not have listed, integral backflow preventers or integral air gaps conforming to Section 608.14.1, IPC 2018 require backflow prevention. Specify the type of backflow prevention device required for each water connection. Reference: Sections 608.1 and 608.3, IPC 2018. 7. At a minimum, coffee machines and non-carbonated beverage dispensers require the use of a backflow preventer listed to either ASSE 1022, ASSE 1024, or an air gap. Reference: Section 608.17.1.2, IPC 2018. 8. The FFE for the Boiler Room (1983) is less than 12" above the rim elevation of manhole MH-4. Provide a backwater valve for the building drain from the Boiler Room. Reference: Section 714.1, IPC 2018 as amended by the City of Tucson. 9. Provide roof drainage and hydraulic scupper size calculations based on the 100-year hourly rainfall rate for Tucson, 3" per hour. Reference: Sections 1101.7, 1106, and 1108, IPC 2018. 10. Show the location of the elevator sump pumps, the route and size of their discharge piping, and their termination points. Reference: Section 107.2.1, IBC 2018. 11. Provide a complete diagram of the natural gas distribution system showing the all of the loads, developed lengths, and the layout of the distribution piping. Reference: Section 402.2, IFGC 2018. 12. Revise detail 2/P 07.01, locating the sediment trap downstream of the shut off valve. Reference: Section 408.4, IFGC 2018. |
08/09/2019 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Identify the manufacturer and model for rooftop units RTU-1 through RTU-13. Reference: Section 107.2.1, IBC 2018. 2. Demonstrate energy code compliance for the building envelope and the mechanical systems using calculations based on the current code. Reference: Sections C101.3, C101.5, C103.2, C303, and C401.2, International Energy Conservation Code 2018. 3. Provide heating and cooling load calculations to justify the heating/cooling capacities of the specified HVAC units (e.g. chillers). Reference: Section C403.1.1, IECC 2018. 4. Provide calculations to verify that adequate ventilation will be provided for the occupied spaces. Reference: Section 407.1, IMC 2018 and Section 7.1, ASHRAE Standard 170-2017. 5. Provide structural calculations and details to show how the Computer Room AC units are to be connected to the building structure. Reference: Section 302.1, IMC 2018. 6. Condensate drains may not terminate over a roof drain unless the roof drain itself terminates at or below grade in an area capable of absorbing the condensate flow without surface drainage. Reference: Section 307.2.1, IMC 2018, as amended by the City of Tucson. 7. Provide the quantity of Nitrous Oxide stored in the medical gas room. Reference: Section 502.9.1, IMC 2018. 8. Provide a description of the dryer exhaust system (e.g. does the system include a power ventilator, backdraft damper, etc.). Show the size and termination of the dryer exhaust duct. Reference: Section 107.2.1, IBC 2018. 9. Show how the clothes dryer exhaust duct will maintain the fire-resistance-rating of the floor-ceiling assembly that it penetrates. Reference: Section 504.2, IMC 2018. 10. Provide the vertical riser of the dryer exhaust duct with a cleanout. Reference: Section 504.3, IMC 2018. 11. Show how the dryer installation complies with Section 504.6, IMC 2018. 12. Provide access for the dryer lint filter. Reference: Section 107.2.1, IBC 2018. 13. The horizontal length of the grease duct serving exhaust fan EF2-3 is in excess of 75-feet. Show the location of the grease duct reservoirs and the slope of the grease duct. Reference: Section 506.3.7, IMC 2018. 14. Show the location and sizes of the grease duct cleanouts for the grease duct serving exhaust fan EF2-3. Reference: Section 506.3.8, IMC 2018. 15. Provide construction details of the grease duct enclosure from the Type I grease hoods to the termination of the grease duct at fan EF2-3. Verify that the grease duct enclosure does not enclose other ducts, pipes or wiring systems. Reference: Section 506.3.11, IMC 2018. 16. Provide a list of the cooking appliances that are to be installed under each Type I hood and show that they have adequate coverage by the hood. Reference: Section 507.1 and 507.2, IMC 2018. 17. Show that the automatic operation of the Type I hoods complies with the requirements of Section 507.1.1.1, IMC 2018. 18. Provide structural calculations and details to show that the Type I hoods are supported from the building structure in accordance with Section 507.2.4, IMC 2018 (the hood hanging weight plus the weight of personnel working in or on the hood). Reference: Section 302.1, IMC 2018. 19. Show that the Type I hood installations comply with Section 507.2.6, IMC 2018 for clearances. 20. The hazardous exhaust duct to EF4-5 penetrates both a floor/ceiling assembly and a fire-resistance rated partition. Provide an enclosing fire-resistance rated shaft for the duct. Reference: Section 510.7.2 and 510.7.3, IMC 2018. 21. Show how the machinery room will be ventilated (i.e. exhausted during normal operating conditions). Provide the normal exhaust volume and the sequence of operation. Reference: Sections 1105.6 and 1105.6.3.1, IMC 2018. 22. Revise the location of the termination of the refrigerant relief vents to provide at least 20-feet of clearance from the ventilation openings for the building. Reference: Section 1105.7, IMC 2018. |
08/13/2019 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | FROM: David Rivera PDSD Zoning Review Section PROJECT: T19CM05078- New Building (Commercial - Hospital) Building Plan Review (1st Review) Northwest Medical Center 2200 S. Houghton Road - PAD 25 Zoning - Related to DP19-0164 TRANSMITTAL DATE: August 13, 2019 DUE DATE: August 20, 2019 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. COMMENT: Zoning has done a cursory review of the building plans. Prior to a more comprehensive review by zoning the DP must be reviewed and approved prior to zoning approval of the building plans. While the cursory review did yield an indication that the building plans are consistent with what has been proposed and drawn on the DP, zoning cannot approve the building plans at this time. In addition, while the building are consistent as it relates to the zoning review purview (as noted above) zoning cannot approve the building plans until the Commercial Plans reviewer(s) have approved the building plans. 2. COMMENT: Zoning will review the building plans on the next submittal to assure consistency with the DP. If any changes are necessary to the building plans due to plan review comments that affect zoning requirements the DP will have to be revised to reflect the changes. Once the DP is approved by all reviewers and the building plans are approved by the Commercial Plans reviewers zoning can approve the building plans. If you have any questions about this transmittal, Contact David Rivera on Tuesday or Wednesday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: building plans |
08/13/2019 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | T19CM05078 1. Sheet G00.13; Plan Review Data (Building Height and Area): The information indicated references Table 503. This is from the 2012 IBC. Please revise the allowable height to Table 504.3 (180') or Table 504.4 (5 stories), and the allowable area to Table 506.2 (Unlimited). Revise the allowable requirements as needed. 2. Sheet G00.13; Plan Review Data (Building Height and Area): The automatic sprinkler system increase references Section 504.2. Please revise the reference to the 2018 IBC table, and revise the allowable requirements as needed. 3. Sheet G00.13; Plan Review Data (Building Height and Area): The total allowed area increases reference Sections 506.2 and 506.3. Please revise the reference to the 2018 IBC section and table, and revise the allowable requirements as needed. 4. Sheet G00.13; Plan Review Data (Occupant Type and Load): A note below the table indicates to refer to plan for individual space occupancy loads. Please add a reference in this note for the sheet numbers with this information. In addition, add the total occupant load for each level on those plans. 5. Sheet G00.13; Plan Review Data (Occupant Type and Load): The occupant type references Section 308.4. Please revise the reference to the 2018 IBC section with this information. 6. Sheet G00.13; Plan Review Data (Occupant Load): The occupant load references Table 1004.1.2. Please revise the reference to the 2018 IBC table and revise the requirements as needed. 7. Sheet G00.13; Plan Review Data (Means of Egress): The size of the doors references Section 1008.1.1. Please revise the reference to the 2018 IBC section and revise the requirements as needed. 8. Sheet G00.13; Plan Review Data (Means of Egress): The projection into the clear width references Section 1008.1.1.1. Please revise the reference to the 2018 IBC section and revise the requirements as needed. 9. Sheet G00.13; Plan Review Data (Means of Egress): The corridor width references Table 1018.2. Please revise the reference to the 2018 IBC table and revise the requirements as needed. 10. Sheet G00.13; Plan Review Data (Means of Egress): The stairway width references Section 1009.4. Please revise the reference to the 2018 IBC section and revise the requirements as needed. 11. Sheet G00.13; Plan Review Data (Means of Egress): The accessible stairways references Section 1007.3. Please revise the reference to the 2018 IBC section and revise the requirements as needed. 12. Sheet G00.13; General: Please review and revise all section/table references on this sheet to the 2018 IBC corresponding sections/tables. Revise the requirements as needed. 13. Sheet G00.13 (Code Review Data); Sheet G00.20 (Wall Type Schedule): Criteria for rated exterior walls (per IBC Table 602) is listed on Sheet G00.13, but no exterior walls in the schedule indicate a required fire resistance rating. Please verify setbacks as indicated on the enlarged site layouts meet the requirements of Table 602. 14. Sheets G00.40, G01.01, G01.02, G01.03, G02.01, G02.02, G02.03, G02.10, and G02.11: Please provide a north arrow on all plans. 15. Sheet G02.01; First Floor Life Safety Plan: It appears some of the travel distances do not follow the IBC Section 1017.3 for measurement criteria (Exam Secure Room 1124 for smoke barrier, Cath Equipment Room 1539 for exit, OR Gen Room 1522 for exit, Surg/Prep Recovery Room 1751 for exit, Surg/Prep Recovery Room 1780 for exit, Clean Linen Room 1685 for smoke barrier, and HR Director Room 1944 for smoke barrier. Please verify and revise the travel distance path as needed. 16. Sheet G02.01; CEP Mezzanine Life Safety Plan: The exit travel distance from the Emergency Electrical Room 1986 indicates 41'-6". Does this include the distance down the exterior stair? 17. Sheet G02.01; Smoke Compartment Area Table: Please remove SC3-1 from this table. 18. Sheet G02.02; Second Floor Area of Refuge: Area SC2-1 indicates 1188 net square feet for 19 stretchers and 98 occupants. Please verify the total net square feet. 19. Sheet G02.02; Second Floor Life Safety Plan: A note above NICU Room 2612 indicates 73'-6" suite to exit access. Should the note indicate this as the distance to the corridor? Please verify. 20. Sheet G02.02; Second Floor Life Safety Plan: At the horizontal exit door between corridors 2401 and 2005, please indicate travel distances from that door to the exits. 21. Sheet G02.02; Second Floor Smoke Compartment Plan: The lower portion should be designated as SC2-6. Please revise and add to the SC Legend. 22. Sheet G02.02; Smoke Compartment Area Table: Please remove SC3-1 from this table. 23. Sheet G02.02; Second Floor Life Safety Plan: Is the Soiled Hold Room 2217 the only location for the one hour ceiling? Please verify. 24. Sheet G02.03; Third Floor Life Safety Plan: It appears the travel distances do not follow the IBC Section 1017.3 for measurement criteria. Please verify and revise as needed. 25. Sheet G02.10; Fire Protection Requirements: Under the maximum area of exterior wall openings for 30' or greater fire separation distance, please revise to No Limit per the IBC Table 705.8. 26. Sheet A01.31; Third Floor Plan: Per the IBC Section 1510.2.1, this Third Floor is considered to be a penthouse used to enclose elevators that travel to the Roof Level. Is this Third Floor area to be used for elevator, mechanical, or electrical equipment? Please verify. 27. Sheet A02.12; Pharmacy Plan: Please indicate the hazardous materials and quantities on the drawing, and verify the maximum allowable quantities listed in Tables 307.1(1) and 307.1(2) are not exceeded. In addition, verify required control areas as defined in Table 414.2.2. 28. Sheet A02.16; Floor Plan: Please indicate the hazardous materials and quantities for the Med Gas Storage Room 1809, and verify the maximum allowable quantities listed in Tables 307.1(1) and 307.1(2) are not exceeded. In addition, verify required control areas as defined in Table 414.2.2. 29. Sheet A02.15; Floor Plan: The plan title indicates Rooms 1741-1786. Please verify the location of Room 1786 on this plan. 30. Sheet A02.16 (Floor Plan); Sheet A11.13 (Reflected Ceiling Plan): Please reference on Sheet A02.16 to see Sheet A11.13 for the Reflected Ceiling Plan. 31. Sheet A02.17 (Floor Plan); Sheet A11.14 (Reflected Ceiling Plan): Please reference on Sheet A02.17 to see Sheet A11.14 for the Reflected Ceiling Plan. 32. Sheet A02.18 (Floor Plans); Sheet A11.14 (Reflected Ceiling Plan): Please reference on Sheet A02.18 to see Sheet A11.14 for the Reflected Ceiling Plans. 33. Sheet A02.19 (Floor/Mezzanine Plans); Sheet A11.15 (Reflected Ceiling Plans): Please reference on Sheet A02.19 to see Sheet A11.15 for the Reflected Ceiling Plans. 34. Sheet A02.20 (Floor Plan); Sheet A11.15 (Reflected Ceiling Plan): Please reference on Sheet A02.20 to see Sheet A11.15 for the Reflected Ceiling Plan. 35. Sheet A02.21A (Floor Plan); Sheet A02.21B (Reflected Ceiling Plan): Please reference on Sheet A02.21A to see Sheet A02.21B for the Reflected Ceiling Plan. 36. Sheet A02.22 (Floor Plan); Sheet A11.21 (Reflected Ceiling Plan): Please reference on Sheet A02.22 to see Sheet A11.21 for the Reflected Ceiling Plan of the portion of Plan 2A below Grid 7. 37. Sheet A02.24A (Floor Plan); Sheet A02.24B (Reflected Ceiling Plan): Please reference on Sheet A02.24A to see Sheet A02.24B for the Reflected Ceiling Plan. 38. Sheet A02.25A (Floor Plan); Sheet A02.25B (Reflected Ceiling Plan): Please reference on Sheet A02.25A to see Sheet A02.25B for the Reflected Ceiling Plan. 39. Sheets A01.15A, A01.15B, A01.15C, A01.23B, A01.23C, A02.19, A02.25B, A02.26A, A02.26B, A02.40, A02.41, A02.42, and A02.43: Please add the Key Plans to these sheets. 40. Sheet A02.26A (Floor Plan); Sheet A02.26B (Reflected Ceiling Plan): Please reference on Sheet A02.26A to see Sheet A02.26B for the Reflected Ceiling Plan. 41. Sheet A02.28A; Plan Title: Please clean up the title identification below the plan. 42. Sheet A02.28A (Floor Plan); Sheet A02.28B (Reflected Ceiling Plan): Please reference on Sheet A02.28A to see Sheet A02.28B for the Reflected Ceiling Plan. 43. Sheet A02.29A (Floor Plan); Sheet A02.29B (Reflected Ceiling Plan): Please reference on Sheet A02.29A to see Sheet A02.29B for the Reflected Ceiling Plan. 44. Sheet A02.30 (Floor Plan); Sheet A11.21 (Reflected Ceiling Plan): Please reference on Sheet A02.30 to see Sheet A11.21 for the Reflected Ceiling Plan of the portion of Plan 1A east of Grid H and south of Grid 6. 45. Sheets A03.14 and A03.15 (Curtain Walls); Sheet G00.20 (Wall Schedule): Please reference on Sheets A03.14 and A03.15 to see Sheet G00.20 for exterior curtain wall descriptions. 46. Sheet A04.01; South Elevation 3: Please clean up the elevation note and the Grid Line K.6. 47. Sheet A04.11; East Elevation Part A: Near Grid Line 11, Section 1/A06.04 is cut twice. Please verify. 48. Sheet A04.12; Enlarged Elevation Part C: Should the Grid Line K.6 be added to this elevation (per South Elevation 3/A04.01)? Please verify. 49. Sheet A04.13 (Enlarged Elevation Part B); Sheet A04.01 (West Elevation 4): The Enlarged Elevation indicates Part B extends to Grid Line 9, while the Elevation extends to Grid Line 11. Please verify. 50. Sheet A04.13 (Enlarged Elevation Part C); Sheet A04.01 (West Elevation 4): The Enlarged Elevation indicates Part C extends to Grid Line 9, while the Elevation extends to Grid Line 11. Please verify. 51. Sheets A05.01, A05.02, and A05.03; Building Sections: All sections indicate a Fourth Floor. If this is in reference to a future floor, please indicate that on the sections. 52. Sheet A07.05; Sections 5 and 6: These sections indicate a Fourth Floor. If this is in reference to a future floor, please indicate that on the sections. 53. Sheet A08.81; Enlarged Plan 3: A note on the upper wall indicates a non-rated smoke partition. This should be a two hour fire rated shaft wall. Please verify. 54. Sheet A09.43; Elevation 14: Please remove the unnecessary verbiage on this detail. 55. General: Many sheets of elevations, sections, and details indicate a Fourth Floor at different roof levels. If this is in reference to a future floor, please indicate that on those elevations, sections, and details. 56. Sheet ID01.00B; Finish Schedule: Please add a reference on this sheet indicating interior wall and ceiling finishes meet the IBC Table 803.13 for flame spread/smoke developed classifications (Section 803.1.2). 57. Sheets ID02.31 and ID02.32: Are these sheets completed? Please verify. 58. Sheet S1.00; Structural Notes (Codes and Standards): Note 1 indicates the 2012 Edition of the IBC. The City of Tucson adopted the 2018 IBC, and that Edition went into effect on January 1. 2019. Please revise the listed code to the 2018 Edition, and verify all calculations and drawings meet the requirements of that code. 59. Sheets S1.01A through S1.01D: Please provide a Key Plan on these sheets per the architectural plans. Revise the Area references to match the architectural. 60. Sheet S1.01A; Foundation Plan: The Match Line between Areas A and C does not follow the Match Line on Sheet A01.11A. Please verify. 61. Sheet S1.01B; Foundation Plan: The Match Lines between Areas B and C and between Areas B and D do not follow the Match Lines on Sheet A01.12A. Please verify. 62. Sheet S1.01C; Foundation Plan: The Match Lines between Areas A and C and between Areas C and D do not follow the Match Lines on Sheet A01.13A. Please verify. 63. Sheet S1.01D; Foundation Plan: The Match Lines between Areas B and D and between Areas C and D do not follow the Match Lines on Sheet A01.14A. Please verify. 64. Sheets S1.02A through S1.02D: Please provide a Key Plan on these sheets per the architectural plans. Revise the Area references to match the architectural. 65. Sheet S1.02A; Framing Plan: The Match Lines between Areas A and B and between Areas A and C do not follow the Match Lines on Sheet A01.23A. Please verify. 66. Sheet S1.02B; Framing Plan: The Match Lines between Areas A and B and between Areas B and D do not follow the Match Lines on Sheet A01.21A. Please verify. 67. Sheet S1.02C; Framing Plan: The Match Lines between Areas A and C and between Areas C and D do not follow the Match Lines on Sheet A01.23A. Please verify. 68. Sheet S1.02D; Framing Plan: The Match Lines between Areas B and D and between Areas C and D do not follow the Match Lines on Sheet A01.22A. Please verify. 69. Sheets S1.03A through S1.03D: Please provide a Key Plan on these sheets per the architectural plans. Revise the Area references to match the architectural. 70. Sheet S1.03A; Framing Plan: The Match Lines between Areas A and B and between Areas A and C do not follow the Match Lines on Sheet A01.23A. Please verify. 71. Sheet S1.03B; Framing Plan: The Match Lines between Areas A and B and between Areas B and D do not follow the Match Lines on Sheet A01.21A. Please verify. 72. Sheet S1.03C; Framing Plan: The Match Lines between Areas A and C and between Areas C and D do not follow the Match Lines on Sheets A01.22A and A01.23A. Please verify. 73. Sheet S1.03D; Framing Plan: The Match Lines between Areas B and D and between Areas C and D do not follow the Match Lines on Sheet A01.22A. Please verify. 74. Sheets S1.04A through S1.04D: Please provide a Key Plan on these sheets per the architectural plans. Revise the Area references to match the architectural. 75. Sheets S1.04A through S1.04D; Framing Plans: The Plan Title indicates Future Roof Framing Plan. This does not appear to be for the future. Please verify. 76. Sheet S4.01; Detail 1: A note indicates to see Sheet ID02.3 for construction/control joint locations. Please revise the sheet reference. 77. Sheet S4.03; Section 8: Please clear up the 26" x 26" pilaster beyond note. 78. Structural Calculations; Page 1: This page indicates the 2012 Edition of the IBC. The City of Tucson adopted the 2018 IBC, and that Edition went into effect on January 1. 2019. Please revise the listed code to the 2018 Edition, and verify all calculations and drawings meet the requirements of that code. 79. Structural Calculations; Page 11: The framing over the Third Floor area is not legible. Please revise. 80. General: Please provide a detail(s) at the knock out panel in the exterior stud wall (see Sheet S1.01B on Grid Line J). 81. General: Please provide a Special Inspection Certificate with Parts A and B completed. Include the type of special inspection (Category), and the name of the person who will be performing that inspection (Special Inspector). This form may be found on our website at www.tucsonaz.gov/PDSD. 82. General: Please provide written responses to all review comments. |
08/13/2019 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. Provide complete compliance with the 2018 IECC for lighting energy compliance. 2. Provide complete compliance with the 2012 Tucson/Pima County Outdoor Lighting Code for the exterior lighting. See section 104 for plan submittal requirements. www.tucsonaz.gov/pdsd. 3. Please explain or clarify why the configuration the areas A, B, C, and D, alternate from the first to second floor plans. 4. Ref; Line diagrams, details, plan sheets E00.03, E00.04, E05.00, E06.00. (a) Provide a complete line diagram for the Main electrical service and all downstream equipment. Show complete lines (feeders )from equipment point A to point B include all OCPD's sizes and ratings, in MSB-1, MSB-2, transformers (disconnects), GSB, generators, transfer switches, and any other electrical distribution equipment, and identify the load served. Include voltage, phase, amp ratings, AIC ratings for all equipment. Also provide a complete fault current analysis and total building service load. See the City of Tucson Commercial Plan Submittal Requirements (Electrical). This document can be printed or downloaded from www.tucsonaz.gov/pdsd. (b) Provide complete grounding details including all grounding and bonding conductor sizes and types. Include details for transformers, generators, GSB distribution panel. NEC 250. (c) Identify all the transformers shown on the line diagrams and correlate with the transformers shown in the electrical room details. (d) Please address the bonding of panels as required per NEC art 517.14. (e) Ref; Plan Sheet E05.01. All egress doors to comply with NEC art 110,26C(3). (f) Some of the wording on plan sheet E06.00 is over lapping, (emergency generator details). Please space the words correctly to make the descriptions more legible. (g) Show power requirements for the elevator pits or equipment rooms. Include feeders, OCPD's, and power source for the elevator control cabinets, also correlate with NEC art 620.22, 620.24, 620.85. Designate branch circuits and panels for lighting and power in the pits and or equipment rooms. "Circuit to spare breaker in nearest normal panel" is unacceptable. (h) Show conduit, feeder sizes and types, panel designations for the elevator power shown on detail 7, plan sheet E06.00, KEYNOTE #4. Please clarify what is meant by " REFER TO ELECTRICAL POWER PLANS FOR SIZES AND CIRCUIT INFORMATION.( could not locate this information in the power plans ) LOCATE BY ROOM ENTRANCE"? Please clarify. 5. Elevators not shown in the equipment schedules or line diagrams. Please clarify. 6. Ref; Lighting plans E01.11 thru E01.23. (a) Plan sheet E01.21, E01.22. Could not locate TYPICAL PRIVATE ROOM lighting detail as stated in the square block note. Referenced layout on sheet E05.04. (b) Plan sheet E01.22. Could not locate PRIVATE BARIATRIC ROOM LIGHTING layout as stated in the square block. Referenced layout on plan sheet E01.21. (c) Plan sheet E01.23. The floor plan at the top right NICU room does not match the detail shown for NICU on plan sheet E05.03. Please clarify. (d) Where is the LIGHTING CONTROL CIRCUIT DESIGNATION LEGEND per general note 'G' shown on the lighting plans? (e) Identify which luminaires are connected to "NORMAL BRANCH", "CRITICAL BRANCH", and "LIFE SAFETY BRANCH". 7. Ref; Power floor plans. Show branch circuit and panel designations for the receptacles and any other powered equipment in the patient rooms. Also verify that the receptacle quantity and branch circuit installations comply with NEC 517- 18A, B, and C, also 517.19A,B. And 517 part 3. 8. Ref; Plan Sheet E02.12. The receptacles have no branch circuits or panel designations. Some rooms have no receptacles in them. Please clarify. 9. Ref; Plan Sheet E05.05 Kitchen. Provide Ground Fault protected receptacles in the Kitchen and food prep areas as required per NEC art 210.8B2. 10. Ref; Roof Electrical Plans E04.11, E04.12, E04.13. Provision for a 120 volt GFI protected service receptacle (s) to be located within 25' of all rooftop mechanical equipment that may require servicing. NEC 210.63. 11. Ref; Plan Sheet E05.06. Provide compliance with NEC 517.19C for the operating rooms. 12. Ref; Panel schedules, Plan Sheets E07.00 thru E07. 06. Please be more descriptive, or provide more detail as to the locations, room numbers, in the branch circuit descriptions for all the outlets, equipment, devices. Example; room numbers, corridors, or other area descriptions. NEC 408.4. 13. Provide for a Selective Coordination analysis of power systems overcurrent devices as required per NEC articles 240, 517, 620, 645, 695, 700.32, 701.27, by the Electrical Engineer of record and to be submitted to the AHJ prior to final electrical inspection approval. Due to the nature of the plan review comments, additional comments may be generated at the subsequent review. Ref; 2018 IBC sec 107.2.1, 2017 NEC, 2018 IECC, 2012 Tucson/Pima County Outdoor Lighting Code. City of Tucson Commercial Plan Submittal Requirements. |
08/19/2019 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Reqs Change | 1) The Development Package needs to be approved prior to Engineering approving the Building Package 2) Coordinate with the Development Package to ensure that all applicable roof drains scupper under sidewalks/pedestrian pathways |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
02/22/2020 | PMARTIN1 | OUT TO CUSTOMER | Completed |