Permit Number: T19CM04509
Parcel: 141186070

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T19CM04509
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/26/2019 MARTIN BROWN FIRE REVIEW Reqs Change Correct code reference editions to 2018 IFC
06/26/2019 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Provide plans signed and sealed by an Arizona Registrant. Reference: Arizona Revised Statutes 32-125, Board of Technical Registration Rules R4-30-304.
2. The International Plumbing Code, 2018, is the controlling code for this activity, not the 2012 International Plumbing Code. Reference: Section 101.2, IPC 2018.
3. Show the storage water heater, thermal expansion tank, and hot water recirculation system installed correctly and in a manner consistent with the Code and the manufacturer's instructions (e.g. shut off valve and check valve locations relative to the thermal expansion tank and the location of the hot water return pipe). Reference: Sections 303.2 and 607.3, IPC 2018.
4. Provide an automatic faucet for the lavatory, dispensing a maximum of 0.25 gallons per metering cycle. For accessibility, the automatic faucet shall operate for at least 10-seconds. Reference: Section 419.6, IPC 2018, as least by the City of Tucson and Section 606.4, ICC/ANSI A117.1-09.
5. Provide an approved vacuum relief valve for the scheduled bottom-fed water heater that is located above the fixture outlets. Reference: Section 504.2, IPC 2018.
6. Verify that all of the vents (except for vents serving interceptors located outdoors) rise vertically to at least 6" above the flood rims of the fixtures they protect prior to running horizontally (e.g. water closets, floor drains). Reference: Section 905.4, IPC 2018.
06/26/2019 ROBERT SHERRY WATER REVIEW Denied 1. Show the location of the proposed water meter, backflow preventer, and the water service pipe on a site plan. The development package is not a substitute for a complete site plan. Reference: Section 107.2.5, IBC 2018.
2. Verify the water pressure available to the site. Per Tucson Water (Ray Muñoz, 520-837-2207), the water pressure range for this address will be approximately 32 to 39 PSI.
07/01/2019 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Provide plans signed and sealed by an Arizona Registrant. Reference: Arizona Revised Statutes 32-125, Board of Technical Registration Rules R4-30-304.
2. Demonstrate energy code compliance for the building envelopes of the car wash and the pay station using calculations based on the current code. Reference: Sections C101.3, C101.5, C103.2, C303, and C401.2, International Energy Conservation Code 2018.
3. Show how one of the "Additional Efficiency Package Options" (C406, IECC 2018) is to be accomplished. Reference: Section C401.2, IECC 2018.
4. Provide heating and cooling load calculations to justify the heating/cooling capacities of the specified HVAC units. Reference: Section C403.1.1, IECC 2018.
5. Clarify the air balance for IDU-1; it is scheduled for an air flow rate of 990 CFM but the balancing data on sheet M210 only identifies 685 CFM of supply air. Reference: Section 304.1, IMC 2018.
07/02/2019 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1.Provide plans signed and sealed by an Arizona Registrant. Reference: Arizona Revised Statutes 32-125, Board of Technical Registration Rules R4-30-304.
2. The City of Tucson has adopted the 2018 International Codes and 2017 National Electric Code , revise plans to the 2018 International Codes and 2017 NEC . IBC 107.2.1.
3. Provide code analysis for the minimum number of required plumbing fixtures . IBC 2902.,IBC 107.2.1.
4. The maximum floor area allowance per business occupant is 150 , amend plans accordingly . IBC Table 1004.5.
5. Sheet P300 references the California Building Codes for design , the City of Tucson has adopted the 2018 International Codes , please amend plans . IBC 107.2.1.
6. Provide a Lintel / Header schedule for the Masonry construction . IBC 107.2.1.
7. Provide plans , structural calculations , etc. for proposed solar canopies . IBC 107.2.1.
8. Provide a completed Special Inspection Form for this project per structural plans . IBC 107.2.1.
07/15/2019 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please address the following electrical plan review comments. Also provide a written response.
1. Ref; Cover Sheet. Revise the NEC code reference to the current 2017 NEC. Also revise the IECC reference for the current 2018 IECC.
Ref; 2018 IBC sec 107.2.1, 2018 IECC, 2017 NEC
07/23/2019 DAVID RIVERA ZONING REVIEW Reqs Change FROM: David Rivera
PDSD Zoning Review Section

PROJECT: T19CM04509 - Commercial Use Group - Automotive Service Full Service Car Wash
Building Plan Review (1st Review) "Surf Through Express Car Wash"
10206 E Old Vail Road - Current C-1 to I-1 Zoning (C9-18-21)

TRANSMITTAL DATE: July 23, 2019

DUE DATE: July 24, 2019

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.


1. COMMENT: Zoning has done a cursory review of the building plans. While the building review did yield an indication that the building plans are consistent with the current version of the Development Package DP19-0149 (still under review) zoning cannot approve the building plans at this time.

2. COMMENT: Zoning will review the building plans on the next submittal and do a comparison to the DP if available to assure consistency with what is proposed on the DP drawings as it relates to the zoning review purview (Building footprint, Height, square footage, site conditions etc.) and on this project any rezoning conditions of rezoning case C9-18-21. Also zoning cannot approve the building plans until the Commercial Plans reviewer(s) have approved the building plans.

3. COMMENT: If any changes are necessary to the building plans due to plan review comments that affect zoning requirements the DP will have to be revised to reflect the changes. Once the DP is approved by all reviewers and the building plans are approved by the Commercial Plans reviewers zoning can approve the building plans.

4. COMMENT: The site plan included in the building plan package does not match the site that is being reviewed for the development package. Assure that the inconsistencies between the two site plans are corrected.

If you have any questions about this transmittal, Contact David Rivera on Tuesday or Wednesday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: building plans
07/26/2019 LOREN MAKUS ENGINEERING REVIEW Reqs Change DP must be approved first.

Final Status

Task End Date Reviewer's Name Type of Review Description
11/07/2019 SBORZAK1 REJECT SHELF Completed