Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T19CM03510
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/01/2019 | MESCALA1 | ZONING | REVIEW | Reqs Change | FROM: Martin Escalante PDSD Zoning Review Section PROJECT: T19CM03510 - The Human Bean - Coffee Shop Building Plan Review (3rd Review) - Related to DP19-0110 6295 E 22nd Street - C-2 Zoning TRANSMITTAL DATE: October 1, 2019 DUE DATE: October 22, 2019 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. *** Note: Previous comments still applicable. 1. COMMENT: Zoning has reviewed the Building plans for compliance with the unapproved version of the development package. While the building footprint and the site revisions are consistent with the unapproved version of the DP as it relates to the zoning review purview (Building footprint, Height, square footage, site conditions etc.) zoning cannot approve the building plans until the PDSD Commercial Plans reviewers have approved the building plans. 2. COMMENT: Zoning will review the building plans on the next submittal to assure that any revisions made to the building plans do not affect zoning requirements and that all PDSD commercial plans reviewers have also approved the building plans. If you have any questions about this transmittal, Martin Escalante at (520) 837-4082 or by email Martin.Escalante@tucsonaz.gov or contact Steve Shields at (520) 837-4956 or email Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: as noted above |
| 10/07/2019 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Approved | |
| 10/14/2019 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 10/18/2019 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | The COMcheck assembly description indicates that the roof has R-38 cavity insulation and R-38 continuous insulation. The drawings show only R-38 cavity insulation for the roof. Coordinate the COMcheck assembly description and the roof design. [Second comment: Comment not addressed.] [Initial comment: Provide calculations for the building envelope to demonstrate compliance with the energy code (e.g. COMcheck). Reference: Sections C103.2 and C401.2, International Energy Conservation Code 2018.] |
| 10/23/2019 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Reqs Change | After outstanding review comments from mechanical have been addressed engineering can approve the building plans |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 10/23/2019 | SBORZAK1 | REJECT SHELF | Completed |