Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Permit Number - T19CM03297
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/10/2019 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Approved | |
05/15/2019 | MARTIN BROWN | FIRE | REVIEW | Approved | |
06/05/2019 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. Ref; Plan Sheet PV-4, PV-5. (a) Locate the under canopy lighting on the plans and designate a branch circuit and panel. Indicate the location of the panel and provide more detail of the wiring methods utilized for the lighting. (b) The 'Lighting Feed' detail states "QTY 1 Light Fixture" but it appears to show 4 fixtures wired in parallel. Please clarify. 2. Ref; Title Sheet P-0, and the line diagrams. The Scope of Work indicates that the PV interconnection will be on the supply side of the existing service CT, but the line diagrams show the interconnection at a 15 amp OCPD. Please clarify. 3. Ref; Plan Sheet PV-3, (a) Provide more detail for the 'Bonding Path Detail', and verify compliance with NEC 690.43A and B. (b) The two smaller details under the 'Bonding Path Detail' are not legible due to small text size. Please enlarge to a minimum font of 3/32". (c) Indicate the mounting height above grade for the inverter in the inverter detail and verify compliance with NEC 690.15A, 705.70. Ref; 2018 IBC sec 107.2.1, 2017 NEC art 690,705. |
06/06/2019 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | From: David Rivera Zoning Review Section June 6, 2019 1. Zoning cannot approve the building plans until DP19-0104 is approved. 2. Once the DP is approved and all commerial plans reviewers have approved the building plans zoning will also approve the building plans. |
06/10/2019 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
06/26/2019 | AVAUGHN1 | APPROVAL SHELF | Completed |
06/26/2019 | AVAUGHN1 | OUT TO CUSTOMER | Completed |
06/26/2019 | AVAUGHN1 | REJECT SHELF | Completed |