Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T19CM03164
Parcel: 136061560

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T19CM03164
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/13/2019 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Correct the size of the gas pipe serving AC-1 and Ac-6 (144 CFH at 150-feet).
2. Verify that the maximum pipe length or piping water volume beyond the recirculating water system complies with Table C404.5.1, IECC 2018.
05/13/2019 ROBERT SHERRY WATER REVIEW Completed
05/14/2019 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Provide energy code compliance calculations for the additions to the building envelope (e.g. COMcheck); use the climate zone for Tucson. Reference: Sections C402, C502.1, International Energy Conservation Code 2018.
2. Show that the proposed walk-in cooler complies with the requirements of Section C403.10.2, IECC 2018.
3. The wall located adjacent to North end of the Type I hood has combustible supports. Revise the wall construction or show how the clearances comply with Section 507.2.6, IMC 2018.
4. The outside air and make-up airflow rates significantly exceed the exhaust airflow rates. Show how over-pressurization of the building will be avoided. Reference: Section 501.4, IMC 2018.
5. Coordinate the location of the termination of the dryer exhaust vent with the electrical engineer.
6. Provide make-up air for the clothes dryer. Reference: Section 504.6, IMC 2018.
05/20/2019 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Approved
06/06/2019 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please address the following electrical plan review comments. Also provide a written response.
1. Provide complete electrical service load calcs and other information with the electrical line diagram. See City of Tucson Commercial Plan Submittal Requirements (Electrical). Justify that the service entrance has the capacity for the additional loads and panels 'L1', 'K1', 'M1'.
Ref; 2018 IBC sec 107.2.1, 2017 NEC art 220,230, City of Tucson Commercial Plan Submittal Requirements (Electrical). www.tucsonaz.gov/pdsd. Submittal Requirements.
06/10/2019 STEVE SHIELDS ZONING REVIEW Reqs Change PDSD TRANSMITTAL

FROM: Steve Shields
Section Manager

PROJECT: Moose Lodge
T19CM02442
Building Plan (1st Review)

TRANSMITTAL DATE: June 10, 2019

1. The building plans have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed.

2. The building plans have been reviewed for compliance with development package DP19-0100 and although it appears that the building plans meet the requirements of DP19-0100 Zoning cannot approve the building plans until the development package has been approved.

3. Until all other PDSD review agencies have approved the building plans zoning cannot approve.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956
06/13/2019 JOHN VAN WINKLE ENGINEERING REVIEW Reqs Change T19CM03164

1) Engineering cannot approve the building plans until the Development plan (DP19-100) has been approved, and all outstanding reviews comments have been addressed

John Van Winkle, P.E.
John.VanWinkle@tucsonaz.gov