Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T19CM02763
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/03/2019 | ROBERT SHERRY | WATER | REVIEW | Completed | |
05/07/2019 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Provide a specification for "EGA" exhaust grille. Reference: Section 107.2.1, IBC 2018. 2. Show how the service bay general exhaust system is to be balanced. Reference: Section 403.3.1.5, IMC 2018. 3. Clarify the type of rain guards that will be used on the utility fan sets. Reference: Section 501.3.2, IMC 2018. |
05/07/2019 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Revise the size of the main natural gas pipe serving AC-3 and AC-9 (a total input of 252 CFH). Per Table 402.4 (2), the maximum demand that a 1" schedule 40 carbon steel pipe can supply at 70-feet is 237 CFH. Reference: Section 402.4, IFGC 2018. 2. Coordinate the gas piping diagram with the gas piping shown on the plumbing roof plan, sheet P1.2. The labels for regulators R-3 and R-4 are reversed. Reference: Section 107.2.1, IBC 2018. 3. Primary rainwater leaders may not discharge onto a sidewalk. Reference: Section 7-01.4.1 E, Technical Standards Manual, Tucson Arizona Unified Development Code. 4. Clarify the fixture description for the emergency eyewash, P-11, which notes, "…air admittance valve for vent." The plumbing waste plan shows a floor drain, P-8, by the eyewash and the drain is shown with an individual vent. Reference: Section 107.2.1, IBC 2018. 5. The rim elevation of the next upstream sanitary manhole (5831-19, 2551.8') is more than 12"below the first floor elevation (2553.00'). A backwater valve shall not be installed per Section 714.1, IPC 2018, as amended by the City of Tucson. 6. An approved development plan is not to be used for construction of on-site utilities (e.g. water service to the building, building sewer, etc.). Remove the "reference only" description from the civil plan, C4.3, showing the installation of the water service to the building and the installation of the building sewer. Reference: Sections 104.2 and 107.2.1, IBC 2018. |
05/13/2019 | MARTIN BROWN | FIRE | REVIEW | Approved | |
05/13/2019 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | T19CM02763 1. Sheet T1.0; Code Review Checklist (Allowable Area Calculation): The Allowable Area indicates 38,295 SF, which includes a 75% increase for frontage and a 200% increase for automatic sprinklers. Using the appropriate factors, please indicate on this sheet how the Allowable Area was determined using Table 506.2 and Section 506.3.2. 2. Sheet AC1.0: Building Area Calculation: Sheet T1.0 indicates the Occupancy Groups for this addition include B and S-1. Please indicate in the Building Area Calculation the breakdown of the SF shown on AC1.0 for each of these two Occupancy Groups. 3. Sheet A0.0; Exit Requirements; Number of Exits; Number of Accessible Exits: It appears the code section references for these requirements are from the 2012 IBC. Please revise. 4. Sheet A1.0; Floor Plan: Per the IBC Section 1109.2, each toilet room shall be accessible unless one of the seven listed Exceptions is applicable. It appears the two restrooms on the east side of the Break Room should be accessible. Please verify. 5. Sheet A4.0; Detail 6: The City of Tucson requires all lettering (upper and lower case) to be a minimum of 3/32" in height. Please revise the Detail dimensions. 6. Sheet A6.0; Sections 1 and 4: These Sections indicate the masonry wall extending to the top of the foundation, while the referenced Details 10/A6.3 indicate a concrete foundation at the same location. Please coordinate. 7. Sheet A9.0; Detail 10: Please indicate on this Detail the top elevation of the steel post, or indicate a reference for that information. 8. Sheet A9.0; Detail 10: Please indicate on this Detail the elevation of the bottom leg of the steel angle (Keynote 10), or indicate a reference for that information. 9. Sheet A9.0; Roof Hatch Detail 6: Per the IBC Section 1011.12.2, a roof hatch to an unoccupied roof must have a minimum of 16 SF with a minimum dimension of 2'. Please verify. 10. Sheet S1.4; Detail 29: Please move the verbiage so it does not overlap the verbiage in Detail 28. 11. Sheet S2.0; Plan Notes: Note 13 references Detail 70/S1.5. Please revise that reference. 12. Sheet S2.0; Plan Notes: Note 15 references Detail 8/S.4. Please revise that reference. 13. Sheet S2.0; Plan Notes: Note 16 references Detail 72/S1.5. Please revise that reference. 14. Sheet S2.0; Plan Notes: Note 19 references Detail 71/S1.5. Please revise that reference. 15. Sheet S3.1 (Roof Framing Plan); Structural Calculations (Sheet 10): The structural calculations indicate Beam DB9 (see calculation Sheet 7) is a W24 x 55, while the Framing Plan indicates a W16 x 31. Please verify. 16. General; Special Inspections: Please add "Site Preparation" and "High Strength Bolting" to the Special Inspection Certificate. 17. General: Please provide written responses to all review comments. Reviewed by Eric Newcomb Contact at 520-837-4911 or Eric.Newcomb@tucsonaz.gov |
05/23/2019 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. Ref; One Line Diagram. (a) Please revise the feeders for panels LP1, LP2, LP3, LP4. Undersized per NEC 240.4, 310.15(B)(16). (b) The load calculation for panel LP5 exceeds the feeder and OCPD amp rating. 2. Ref; Outdoor lumen calcs. The total installed lumens shown in the lumen calculations exceeds the maximum allowable. Ref; 2017 NEC, 2018 IBC 107.2.1, 2012 TUCSON/PIMA COUNTY OUTDOOR LIGHTING CODE. |
05/29/2019 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | FROM: David Rivera PDSD Zoning Review Section PROJECT: T19CM02763 - Related to DP19-0030 New Auto Dealer Building (Porsche Site on 22nd St.) (1st Review) 4690 E. 22nd Street - C-2 Zoning TRANSMITTAL DATE: May 29, 2019 DUE DATE: May 30, 2019 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 01. COMMENT: As of this review the DP for the new Porsche Dealer Ship building has not been reviewed for compliance. 02. COMMENT: Zoning will do a follow up review on the next submittal of the building plans. 03. COMMENT: Once the DP is approved and the Commercial Plans reviewers have approved the building plans, zoning can approve the building plans assuming they are in compliance with the approved DP. If you have any questions about this transmittal, Contact David Rivera on Tuesday or Wednesday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields any time during the week at (520) 837-4956 or email Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised Building Plans |
05/29/2019 | LOREN MAKUS | ENGINEERING | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
05/30/2019 | QJONES1 | APPROVAL SHELF | Completed |
05/30/2019 | QJONES1 | OUT TO CUSTOMER | Completed |
05/30/2019 | QJONES1 | REJECT SHELF | Completed |