Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T19CM01071
Parcel: 136254100

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T19CM01071
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/11/2019 MARTIN BROWN FIRE REVIEW Approved
03/14/2019 RMCCOY1 BUILDING-COMMERCIAL REVIEW Approved
03/25/2019 ROBERT SHERRY WATER REVIEW Reqs Change The plumbing plans call for a 1-1/2" water meter to serve buildings 1 through 6. The development package indicates the location of a meter and backflow preventer to serve buildings 2 through 6 but does not provide their sizes and does not show the pipe sizes for the water service to the buildings. Verify the number of fixture units encompassed by buildings 1 through 6 (assuming that building 1 will be served by this water meter). Coordinate with the civil design and verify the result with Tucson Water.
03/26/2019 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. The COMcheck envelope compliance certificate calls for R-44 cavity insulation in both the high-bay and low-bay roofs with an additional R-5.0 continuous insulation for the low-bay roofs; where is this shown on the plans? Reference: Section 107.2.1, IBC 2018.
2. Provide thermal load and HVAC equipment-sizing calculations to confirm the specified heat pumps for each apartment type. Reference: Sections R302.2 and R403.6, IECC 2018.
3. Revise the note on sheet A6.2 to call for all exterior window types to have the maximum SHGF and U-factors as shown in the COMcheck calculations.
4. Verify that the kitchen hood will exhaust a minimum of 100 CFM (intermittent operation). Reference: Section 403.3.2.3, IMC 2018.
03/26/2019 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. An approved development plan is not to be used for construction of on-site utilities (e.g. water service to the building, etc.). Provide a site plan showing the installation of the water service to the buildings. Note that the civil utilities drawing included in the development package is incomplete and does not show all of the required pipe sizes or the pipe material. Reference: Sections 104.2 and 107.2.1, IBC 2018.
2. A separate permit is required for the installation of a private sewer collection system and will require a review of the system design by the Pima County Department of Environmental Quality. Reference Title 18, R18-9-E302, 4.02 General Permit, Arizona Administrative Code.
3. Revise the design of the hub drain per Section 802.4.2, IPC 2018.
4. Provide the slope of the proposed rain gutters. Reference: Section 1106.6, IPC 2018.
5. Provide secondary roof drains for the roof areas with parapets. Reference: Section 1108.1, IPC 2018.
04/04/2019 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please address the following electrical plan review comments. Also provide a written response.
1. There are 2 plan sheet labeled as E1.1. Please clarify.
2. Ref; 2012 Tucson/Pima County Outdoor Lighting Code.
(a) Provide full compliance with the Tucson/Pima County Outdoor Lighting Code for the exterior building lighting.
(b) There are no panel schedules for the 'S' panels feeding the exterior building lighting. Also there was no line diagrams included in the plan set showing these panels or where they are fed from. Please provide this information on the plans.
3. Provide a complete line diagram for the electrical service(s) equipment and all downstream equipment. Include load calcs, Aic ratings, all feeder sizes and types, grounding, all the panels, and equipment locations on the site. See the City of Tucson Commercial Plan Submittal Requirements (ELECTRICAL), www.tucsonaz.gov/pdsd.
4. Provide a note or indicate what the encircled numbers and or letters represent that are shown along the side of the unit panel schedules.
5. Provide for AFCI branch circuit protection, NEC 210.
6. Provide for Tamper Resistant Receptacles, NEC 406.12, 210.52.
7. Branch circuit for the unit bathrooms shall be dedicated for the bathrooms and have no other outlets. NEC 210.11C(3).
8. The dishwasher receptacle for the units should be GFI protected. NEC 210.8D.
9. The washer receptacles should be GFI protected. NEC 201.8A (10).
10. Some of the branch circuits in the units do not correlate with the unit panel schedules. Please correct either the electric floor plan or the panel schedules.
11. Provide a complete luminaire schedule.
12. Provide compliance with the 2018 IECC section R104.
Ref; 2017 NEC, 2018 IBC sec 107.2.1, 2018 IECC, 2012 Tucson/Pima County Outdoor Lighting Code, City of Tucson Commercial Plan Submittal Requirements.
04/04/2019 LOREN MAKUS ENGINEERING REVIEW Approved
04/05/2019 STEVE SHIELDS ZONING REVIEW Needs Review

Final Status

Task End Date Reviewer's Name Type of Review Description
04/22/2019 AMARTIN1 OUT TO CUSTOMER Completed