Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T19CM01036
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/19/2019 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 02/27/2019 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Approved | |
| 02/27/2019 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet T1.0; Code Review (Allowable Area): Please provide the calculations on this sheet for the allowable area. The 2018 IBC Table 506.2 provides the allowable square footage for the various Occupancy Classifications (use the S1 Category for either B or S-1 Occupancy Classification. Show how the 74.9% allowable area increase for frontage was calculated. 2. Sheet C1.0; Reference Site Plan: The total Service Area addition indicates 2641 SF, while the sum of the areas (665 + 1959 SF) is 2624 SF. Please coordinate. 3. Sheet C1.0; Building Area Calculation: The area of the enclosed existing canopy indicates 1743 SF, while the plan on this sheet indicates 1959 SF. Please coordinate. 4. Sheet A0.0; Life Safety Plan: The restrooms and janitor's closet all indicate "?" for the number of occupants. Please remove the ? (no occupant load is required). 5. Sheet A0.0; Life Safety Plan: The new Service Bays indicate 2552 SF. That number does not match the SF indicated on Sheet C1.0. Please coordinate. 6. Sheet A0.0 (Life Safety Plan); Sheet A2.0 (Reflected Ceiling Plan): The egress plan indicates occupants from the existing areas using the new Service Bay's door on the west wall as an exit. Lighted exit signs must be located at those existing doors that contribute to the discharge load. Please verify the existing doors have those exit signs, or locate new signs on the Reflected Ceiling Plan of Sheet A2.0. 7. Sheet A0.0; Occupant Load Calculations: Is this set of drawings requesting a new C of O for the entire building (per the Occupant Load Calculations Table), or just for the new Service Bays area? Please clarify. 8. Sheet A0.0; Occupant Load Calculations: The Table indicates 18,586 SF on the first floor (5020 + 13,566 SF), and 2890 SF on the second floor (2088 + 479 + 323 SF). Please clarify how these numbers relate to the Building Area Calculations on Sheet C1.0. 9. Sheet A2.0; Proposed Floor Plan: Keynote 6 indicates to see Mechanical plans for details at the fresh air intake. The actual details should reference the structural sheet S2.1. Please revise. 10. Sheet A2.0; Proposed Floor Plan: Keynote 11 was not located on the floor plan. Please verify. 11. Sheet A2.0; Proposed Reflected Ceiling Plan: Keynote 8 indicates to see Mechanical plans for details at the fresh air intake. The actual details should reference the structural sheet S2.1. Please revise. 12. Sheet A2.0; Wall Type Schedule: Please add a reference to Sheet S2.1 for the masonry wall information. 13. Sheet A2.0 (Proposed Floor Plan); Sheet A4.0 (Detail 4): The detail indicates a 6" concrete slab, while the Floor Plan indicates a 5" concrete slab (Keynote 5). Please coordinate. 14. Sheet A3.0; Building Elevation 3: Should this be titled the West Building Elevation? Please verify. 15. Sheet A3.0; Proposed Roof Plan: Please provide structural calculations to verify the existing roof structure can adequately support the new mechanical unit (Roof Plan Keynote 5). 16. Sheet S2.1 (Foundation Plan); Structural Calculations (Sheet 6): The calculations indicate a 2'-0" x 12" wall footing, while the plan indicates a 1'-4" x 12" wall footing. Please coordinate. 17. Sheet S3.1; Details: The detail to the left of Detail 206 indicates 204. Please revise. 18. Sheet S3.1; Detail 110: The title of Detail 110 should be New Steel Column at Existing Masonry Wall. Please revise. 19. General: Please provide the Special Inspection Certificate with Parts A and B completed. 20. General: Please provide written responses to all review comments. Reviewed by Eric Newcomb Contact at 520-837-4911 or Eric.Newcomb@tucsonaz.gov |
| 03/04/2019 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. A splash pad located on a concrete slab is not an approved location for the termination of a drain from an evaporative cooler. Reference: Section 307.2, IMC 2018. 2. Provide justification for not providing a source-capture exhaust system for the vehicles being serviced. Reference: Section 502.14, IMC 2018. |
| 03/04/2019 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Verify the operating weight of the specified radiant heaters. Reference: Section 107.2.1, IBC 2018. 2. Note 2 for the radiant heater schedule calls for the installation of a "concentric vent termination kit". Show how the radiant heaters are to be installed per the manufacturer's instructions with regard to ventilation of the area above the heaters and dilution of the products of combustion. Reference: Section 305.1, IFGC 2018. 3. Southwest Gas, the local gas utility, provides natural gas at 7" WG, 2 PSIG, and 5 PSIG. The specified radiant heaters require a minimum inlet pressure of 7" WG and will require a gas meter that delivers at least 2 PSIG gas into a regulator located after the meter set. Reference: Section 402.1, IFGC 2018. 4. Based upon Table 402.4 (2), IFGC 2018, a 1-1/4" carbon steel pipe is required for the pipe serving the six radiant heaters (a 1" pipe can serve a maximum of 173 CFH at 125-feet). 5. Detail 1/M2.1 calls for the water supply pipe to the evaporative cooler to be labeled as "non-potable". Provide a backflow preventer between the supply to the evaporative cooler and its connection to the building water distribution system. Reference: Section 608.17.6, IPC 2018. 6. Note: An evaporative cooler is not a plumbing fixture and it is not appropriate to estimate its water demand using fixture units. Reference: Section E102.2.2, IPC 2018. |
| 03/04/2019 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 03/08/2019 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 03/13/2019 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | FROM: David Rivera PDSD Zoning Review Section PROJECT: T19CM01036 - Retail Use - Vehicle Rental and Sales (Used Auto Sales) Building Plan Review (1st Review) - Related to DP19-0031 6001 E. Speedway Boulevard - C-2 Zoning TRANSMITTAL DATE: March 13, 2019 DUE DATE: March 15, 2019 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. COMMENT: Zoning has reviewed the Building plans for compliance with the unapproved version of the development package. While the building footprint and the site revisions are consistent with the unapproved version of the DP as it relates to the zoning review purview (Building footprint, Height, square footage, site conditions etc.) zoning cannot approve the building plans until the PDSD Commercial Plans reviewers have approved the building plans. 2. COMMENT: If available, include a reference copy of the PDSD approved and signed version of the DP with the next submittal of the building plans package. The unapproved version of the DP included in the building package set shall be replaced with the PDSD approved and signed version or the dp sheets must be marked as reference only. 3. COMMENT: Zoning will review the building plans on the next submittal to assure that any revisions made to the building plans do not affect zoning requirements and that all PDSD commercial plans reviewers have also approved the building plans. If you have any questions about this transmittal, Contact David Rivera on Tuesday or Wednesday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: as noted above |
| 03/21/2019 | LOREN MAKUS | ENGINEERING | REVIEW | Passed |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 03/26/2019 | PMARTIN1 | APPROVAL SHELF | Completed |
| 03/26/2019 | PMARTIN1 | OUT TO CUSTOMER | Completed |
| 03/26/2019 | PMARTIN1 | REJECT SHELF | Completed |